Project PI Planning settings

What this page is — the PI Planning tab of a project's settings: six sub-tabs that hold the defaults for every PI Planning session the project runs, and the list of teams that plan in it.

What it is for — so the Release Train Engineer prepares each planning event from the train's own standards instead of rebuilding the same lists, people and defaults every quarter.

The problem it solves — without project defaults, every new session starts from the generic SAFe lists. A train that has agreed its own readiness checklist, its own Scrum of Scrums questions or its own working agreements has to retype them each time, and two sessions of the same train end up running by different rules.

Route: /org/projects/…?tab=pi_planning (Project → Project sections → PI Planning) · Permission to view: Open PI Planning sessions read-only: brief, team boards, program board, risks, discussion, objectives and review. · Permission to change: Create, edit and close PI sessions, choose the participating teams, and edit the project's PI Planning settings.


1. What the tab holds​

The tab is a row of six sub-tabs. Each one keeps one kind of default, and each is saved on its own.

Sub-tabWhat it keepsWho uses it during the eventCan one session keep its own list?
Planning sessionsWhich Planning page the project leans on, the default session length, the default facilitator, the confidence vote switch, the teams linked to the projectWhoever creates a sessionThe facilitator and length are pre-filled and can be changed in the session's setup
Roles & permissionsThe rule book: what each role sees and may change in a sessionEvery participantNo. It applies to every session of the project at once. See Roles and permissions
ART readinessThe checklist the RTE works through before the eventThe RTEYes, the RTE or a PI Planning manager
Scrum of ScrumsThe checkpoints every team answers during Team breakoutsTeams and the RTEYes, the RTE, while the session is open
Management reviewThe questions management works through at the end of Day 1The management teamYes, the management team
Working agreementsHow the train behaves during the event; everyone agrees to them when they joinEveryoneYes, the management team; anyone may suggest an addition

How a session uses the four lists​

The four lists — readiness, Scrum of Scrums, management review and working agreements — work the same way. A session follows the project's list until it changes its own. Concretely:

SituationWhat the session shows
The session has never changed the listThe project's current list. If you change the project list later, the session shows the new one, even if it is already running
The session changed its listIts own list. Later changes to the project list, and Reset to defaults on the project, do not touch it
The project never saved a listThe built-in list, with the note This is the built-in list (or …SAFe checklist, …ten built-in questions, …seven SAFe working agreements)

Each list's card says so in its description: Sessions use this list live: a change here reaches every session that has not saved a list of its own. Nothing is copied when a session is created.


2. Why you would use it​

  • Prepare a PI in minutes, not an afternoon. The facilitator, the linked teams and four lists are already in place when the RTE presses New PI session.
  • One train, one set of rules. Two consecutive PIs of the same train ask the same Scrum of Scrums questions and agree the same working agreements, so trends between PIs are comparable.
  • Learn once, keep it. When a retrospective concludes "we need a checkpoint about environments", adding it here makes it part of every future event rather than a note someone must remember.
  • No surprise teams. Only teams linked here can be picked for a session, so a session cannot quietly include a team the project does not plan with.

3. Where it fits in the event​

These settings are read at three moments.

MomentWhat is read
Creating a session (Create a session)Default facilitator, default session length, linked teams (all of them are ticked), and the confidence vote switch for the default agenda
Before the eventThe ART readiness checklist on the session's ART readiness tab (ART readiness)
During the eventScrum of Scrums checkpoints during Team breakouts, management review questions at the end of Day 1, working agreements when each person joins, the rule book and the confidence vote switch throughout — all read live

4. Planning sessions​

Figure 1 — Planning sessions: the session defaults and the teams that plan in Optima Orbit.
#ElementWhat it does
1The six PI Planning settings tabsPlanning sessions, Roles & permissions, ART readiness, Scrum of Scrums, Management review, Working agreements. Adding &pi=roles, &pi=readiness, &pi=sos, &pi=mgmt or &pi=agreements to the address opens a sub-tab directly
2Which Planning page opens first: Single-team planning or PI Planning (multi-team)With PI Planning (multi-team), opening the project's Planning page from the menu goes straight on to PI Planning. A link into a particular Planning tab or action still opens Planning. With Single-team planning, Planning opens as usual. See the note below
3Default session length (15 minutes to 3 days)Steps of 15 minutes. Used by sessions run on a single clock rather than a timed agenda. A session with an agenda takes its length from the agenda
4Default facilitator — pre-filled on every new sessionAny member of the project, or No default facilitator. Changeable per session
5Confidence vote on or offWhether the project's sessions run a confidence vote at all. See the note below
6The card's descriptionMulti-team planning sessions: their defaults and the teams that plan in this project. The defaults come first, the linked teams under Teams that plan in this project
7Link or unlink teams; each linked team shows its lead, members and FTEPick a team from the list to link it. Each card shows the team's code, lead, member count, FTE, the projects it plans for and its skills. The × on a card unlinks it
Planning page opens on PI Planning

With PI Planning (multi-team), the PI Planning session list shows a Single-team planning button (tooltip: This project's Planning page opens on PI Planning; the single-team Planning page is still here). It opens the single-team Planning page and stays there. That page then shows the banner This project plans with several teams: its Planning page opens on PI Planning. with the link Open PI Planning →.

Figure 2 — When the Planning page opens on PI Planning, Single-team planning is the way back.
#ElementWhat it does
1Single-team planningOpens the project's single-team Planning page and stays there. Shown only when the project's Planning page opens on PI Planning
The confidence vote switch

With Confidence vote off, every session of the project loses its Confidence vote tab, and a Confidence vote agenda item that has not started yet is switched off, so the run skips it. An item that has already run keeps its place. The default agendas of new sessions leave the item switched off. Every session reads the switch live: switching it back on brings the tab back, and switches the agenda item on again if it had not started. While it is off, any attempt to vote answers The confidence vote is switched off for this project (Project settings → PI Planning).

  1. Open the project, then PI Planning → Planning sessions.
  2. In Teams that plan in this project, open the picker (it reads Add a team…) and choose a team. The card appears with the chip Not saved yet.
  3. Repeat for each team, or press × on a card to unlink a team.
  4. Press Save PI Planning at the foot of the card.

A team that is linked here but has members who are not on the project shows a warning naming them: … is not on this project — add them under Project → Team, or they cannot be assigned the team's tasks. This matters on projects restricted to their members.

Field reference​

FieldControlRequiredValidationWhere the values come from
Planning page opens onTwo-way switchYesOne of the twoFixed list: Single-team planning, PI Planning (multi-team)
Default session lengthStepper with − and +Yes15 to 4,320 minutes (3 days), in steps of 15Typed or stepped
Default facilitatorSearchable listNoMust be a user of your organisationThe project's members
Confidence voteSwitch—On by default—
Team pickerSearchable listNoA team must be activeThe organisation's planning teams not yet linked (Planning teams)

The footer reads Last saved with a date and time, or Using defaults until first save. Without the permission to change, it reads Read-only — changing these needs the PI Planning — "Create, edit and close PI sessions, choose the participating teams, and edit the project's PI Planning settings" permission, followed by the permission's code in brackets. The controls show plain text, and there is no Save button.

The same settings inside Task Configuration​

The six sub-tabs are also reachable without opening the project: Task Configuration → Estimation & Sizes shows them under the project's estimation settings (the unit tasks are estimated in and the T-shirt sizes). This is handy when you are already adjusting how a project estimates — capacity in story points on the PI boards and the size rows here belong together.

Figure 3 — The PI Planning settings embedded in Task Configuration → Estimation & Sizes.
#ElementWhat it does
1Task Configuration → Estimation & SizesThe section that carries the embed. The other Task Configuration sections do not show it
2The same six PI Planning tabs as Project settings → PI PlanningPlanning sessions, Roles & permissions, ART readiness, Scrum of Scrums, Management review, Working agreements — each saved on its own, exactly as described on this page
3Changes here and there are the same settings — for the project picked at the top leftSave here and the project's PI Planning tab shows the change, and the other way round. Switching the project at the top left switches the settings too

The embed follows the same permissions: it appears only for roles with the PI Planning view permission, and it is read-only without Create, edit and close PI sessions, choose the participating teams, and edit the project's PI Planning settings. It is not a second copy — there is one set of defaults per project.


5. ART readiness checklist​

Figure 4 — The ART readiness checklist, still the built-in SAFe list.
#ElementWhat it does
1The built-in SAFe checklist until the project changes itShown while the project has no list of its own. The built-in list has sixteen items: ten needed, six desirable
2The item's titleUp to 120 characters. An item with an empty title is dropped when you save
3The question the RTE answersUp to 1,000 characters
4Needed (must be ready before the event) or Desirable (can grow over the first PIs)Needed items are counted on the session's readiness tab as the ones that must be done
5ReorderMove the item up or down
6RemoveTakes the item out of the list (saved when you press Save checklist)

The footer counts the items and how many are needed, up to 40. Save checklist stays grey until the list differs from what is saved. Reset to defaults asks for confirmation — The project goes back to the sixteen SAFe ART readiness items. Sessions that changed their own checklist keep it.


6. Scrum of Scrums, management review and working agreements​

These three sub-tabs are the same editor holding three different lists.

Figure 5 — Scrum of Scrums checkpoints.
#ElementWhat it does
1Whether the project still uses the built-in list or its ownThe note disappears once the project saves its own list
2A checkpoint — click to edit its textType over the text. Up to 300 characters. An emptied line is dropped on save. A new line's placeholder reads A question every team answers…
3Move it up or downChanges the order teams see
4Remove itTooltip Remove the checkpoint. Removes the line
5Add one (up to 30)Add a checkpoint adds an empty line at the end
6Go back to the built-in listAsks for confirmation; available only when the project has its own list
7Save — sessions use this list liveSave checkpoints. Grey until something changed

During Team breakouts each team answers every checkpoint with not started, in progress, done or an issue; the RTE follows all teams on the session's Scrum of Scrums tab. See Scrum of Scrums.

Figure 6 — Management review questions.
#ElementWhat it does
1Whether the project still uses the built-in list or its ownTen built-in questions until the project saves its own
2A question — click to edit its textUp to 300 characters. A new line's placeholder reads A question management answers…
3Move it up or downChanges the order management walks through them
4Remove itTooltip Remove the question
5Add one (up to 30)Add a question
6Go back to the built-in listThe project goes back to the ten built-in questions. Sessions that changed their own list keep it.
7Save — sessions use this list liveSave questions

The questions frame the management team's discussion at the end of Day 1, where it records decisions and actions. See Management review.

Figure 7 — Working agreements.
#ElementWhat it does
1Whether the project still uses the built-in list or its ownSeven SAFe agreements until the project saves its own
2An agreement — click to edit its textUp to 300 characters. A new line's placeholder reads How we work together…
3Move it up or downReorders
4Remove itTooltip Remove the agreement
5Add one (up to 30)Add an agreement
6Go back to the built-in listThe project goes back to the seven SAFe working agreements.
7Save — sessions use this list liveSave agreements

Each participant reads and agrees to the working agreements when they join a session; anyone may suggest an addition, which the RTE accepts or declines. See Distributed events and working agreements.

List field reference​

ListControl per lineLimit per lineLinesEmpty linesSaving with no lines
ART readinessTitle, question, Needed/Desirable120 / 1,000 charactersUp to 40DroppedNot possible: Save stays grey
Scrum of ScrumsOne text field300 charactersUp to 30DroppedNot possible
Management reviewOne text field300 charactersUp to 30DroppedNot possible
Working agreementsOne text field300 charactersUp to 30DroppedNot possible

Repeated spaces inside a line are reduced to one when it is saved. A list that goes over its limit is refused with a message naming the list, such as the Scrum of Scrums list has at most 30 checkpoints, the Management review list has at most 30 questions or the working agreements list has at most 30 agreements; a line that is too long reads, for example, an agreement is at most 300 characters.


7. How a session changes its own list​

ListWhere in the sessionWho may change itWhen
ART readinessART readiness tabThe RTE, or someone with the manage permissionWhile the session is open
Scrum of ScrumsScrum of Scrums tabThe RTEWhile the session is open
Management reviewManagement review tabThe management team: the RTE, Product Manager, System Architect, Business Owners and PI Planning managersWhile the session is open
Working agreementsThe working agreements panelThe management teamUntil the session is closed

Once a session saves its own list, it stops following the project's list for good.

When a session removes a checkpoint or readiness item, the teams' answers to that line are removed with it. A line whose text is only edited keeps its answers.


8. Worked example​

Maya Fernandes is the RTE of the train that plans Optima Orbit.

  1. She opens Projects → Optima Orbit → PI Planning → Planning sessions and sets Default facilitator to herself and Default session length to 480 minutes (8 h).
  2. In Teams that plan in this project she links Phoenix, Atlas and Orion. Each card shows 5 members and 4.5 FTE: the product owner at 50 % and four people at 100 %. The picker now reads Every active team is linked.
  3. She presses Save PI Planning. The footer shows Last saved with the time.
  4. On Scrum of Scrums she keeps the seven built-in checkpoints but, after last PI's retrospective, adds Have you checked your test environment bookings? and presses Save checkpoints. The note This is the built-in list disappears.
  5. On Working agreements she leaves the seven SAFe agreements as they are.

When she later creates PI 2026.4 Planning, the setup is pre-filled with her as facilitator and all three teams ticked. During Team breakouts on Day 1, every team sees eight checkpoints. Atlas marks Have you begun resolving dependencies with other teams? as an issue, which Maya sees on the session's Scrum of Scrums tab.


9. Before this works — what an administrator sets up​

NeededWithout it
Open PI Planning sessions read-only: brief, team boards, program board, risks, discussion, objectives and review.The PI Planning tab does not appear in the project's settings
Create, edit and close PI sessions, choose the participating teams, and edit the project's PI Planning settings.Everything is read-only, and the team picker is not shown
Planning teams set up in Organization Settings → Planning TeamsThe picker is empty: No teams yet. Teams are set up in Organization Settings → Planning Teams
See the organisation's planning teams, their members and projects.The linked teams still show, but each person's share across all teams (over-100 % warnings) is missing
Team members added to the project (projects restricted to their members)The team card names them as not on the project, and they cannot be given the team's tasks
Milestones for the PI and its iterations (Project Planning settings)Not needed here, but a session cannot be created without them

10. What these settings affect​

PlaceEffect
Session setupFacilitator, length and teams are pre-filled; only linked teams can be picked
A session's ART readiness, Scrum of Scrums, Management review and working agreementsShow the project list until the session saves its own
The project's Planning pageOpens on PI Planning when the project plans multi-team; the single-team page stays reachable
Every session's Confidence vote tab and agenda itemShown and run only while Confidence vote is on
Sessions already publishedKeep their teams if you unlink a team here

11. Don't confuse this with…​

ThisIs notBecause
Project → PI PlanningProject → PlanningPlanning holds the single-team planning settings and the planning words (Iteration, Delivery Block, Feature). See Project Planning settings
Linking a team hereCreating a teamTeams and their members are created in Organization Settings. See Planning teams
Roles & permissions sub-tabThe organisation's rolesThe rule book narrows what each session role does; organisation roles decide who reaches PI Planning at all. See Roles and permissions
A project listA session listA session that changed its list keeps it; the project list only feeds sessions that have not

12. Troubleshooting​

SymptomCause
The PI Planning section is missing from the project's sectionsYour role lacks the PI Planning view permission
Everything is plain text and there is no SaveYour role can view but not change the settings
The team picker reads Every active team is linkedEvery active planning team is already linked. Create more teams in Organization Settings
A team you expect is not in the pickerIt is deactivated, or already linked
Save checkpoints (or questions, agreements, checklist) stays greyNothing changed, or every line is empty
Reset to defaults is greyThe project is already on the built-in list
A running session still shows the old list after you saved a new oneThat session saved a list of its own earlier; edit it on the session's tab
A session has no Confidence vote tabConfidence vote is switched off on Planning sessions
The confidence vote is switched off for this project (Project settings → PI Planning).Someone tried to vote while the switch is off. Switch it on to bring the vote back
Opening Planning from the menu lands on PI PlanningPlanning page opens on is set to PI Planning (multi-team). Use Single-team planning on the PI Planning page to reach single-team Planning
the Scrum of Scrums list has at most 30 checkpoints (or questions, agreements)The list has more than 30 lines. Remove some before saving
The facilitator must be a user of this organisationThe person chosen is no longer an active user
A team card warns that people are not on this projectAdd them under Project → Team
The PI Planning tabs are missing under Task Configuration → Estimation & SizesYour role lacks the PI Planning view permission
A change made under Task Configuration "did not stick" on another projectThe embed edits the project picked at the top left of Task Configuration; pick the other project there