Management review and problem solving

What this page is — a guide to the Management review tab of a PI Planning session: the last activity of Day 1, where the RTE, product management, the system architect and the business owners read what the draft plans show, work through a list of questions, and record the decisions and actions the teams apply on Day 2.

What it is for — turning the problems the draft plans exposed — an over-committed team, a feature that does not fit, a dependency nobody can meet — into clear decisions about scope, priorities, people and risks, and handing them to the teams before Day 2 starts.

The problem it solves — the management review traditionally happens in a closed room with a flipchart. The decisions reach the teams the next morning by word of mouth, half of them are remembered differently by each team, and a feature that was "postponed" is still sitting in a team's Iteration 1 when the final plan is reviewed.

Route: Orbit Ops → PI Planning → open a session → Management review, under Team boards (/org/tasks/pi-planning?project=…&session=…&tab=mgmt_review) · Permission: Open PI Planning sessions read-only: brief, team boards, program board, risks, discussion, objectives and review. Who may record and share is decided by the session's roles and the Management review row of the project's rule book (section 1), not by a separate permission.


1. Who sees it, and when​

The management review belongs to the management team of the session:

  • the RTE (the session's named facilitator),
  • the Product Manager and the System Architect named on the session,
  • the Business Owners named on the session,
  • anyone holding Create, edit and close PI sessions, choose the participating teams, and edit the project's PI Planning settings.

Being on the management team is not enough on its own: the role must also have the Management review row in the project's rule book (Project settings → PI Planning → Roles & permissions). The RTE always has it. A Product Manager, System Architect, Business Owner or PI Planning manager whose role lacks the row reads the review like the teams — only once it is shared — and cannot write it: no questions, notes, decisions or sharing. Reading the review at all needs the Management review, Planning adjustments or Team boards row.

WhoBefore it is sharedAfter it is shared
Management with the Management review rowSees and edits everythingSees and edits; can share again
Management without the rowManagement has not shared its review yetReads it; cannot write it
Everyone else in the sessionManagement has not shared its review yetReads it; the affected team answers scope changes

Management does not change the draft plans here. It records what should change — scope, vision, teams, resources — and the teams make the change on their own boards on Day 2.

The tab opens for management when the facilitator closes the Draft plan review agenda item; until then the sidebar entry carries a lock. It stays editable until the plan is committed.

Management reviewDraft plan reviewPlanning adjustments (Day 2)
Who works in itManagementEvery team presentsThe RTE presents, teams answer
What it producesDecisions and actionsNothing — it readsTeams' answers to the decisions
Changes the boardsNoNoYes, through Accept and apply

2. Why you would use it​

  • Facts, not impressions. The left column reads the teams' work for you: load per team and iteration, features still in the backlog, unanswered dependencies, ART risks, Scrum of Scrums issues, objectives, readiness.
  • A structured conversation. The project's standard questions, with notes typed as the room talks, a Focus mode with a timer, and each question marked Discussed or Parked.
  • Decisions the teams can act on. Each decision names its kind, owner and due time; a scope change names the feature and its effect, and the team can apply it in one click.
  • Nothing lost overnight. Sharing pins a summary for every participant, rings their bell and, if you choose, e-mails it.

3. The screen​

Figure 1 — The management review after it was shared: the facts, the questions, and the decisions.
#ElementWhat it does
1Progress lineQuestions discussed out of the total, decisions and actions recorded, scope changes and how many the teams have answered
2Sharing stateShared with the day, time and who shared it; before that Only management sees this
3Share with the trainHere Share again: opens the share drawer (section 6). Planning adjustments beside it opens the Day 2 tab
4What the day tells usThe facts Orbit reads from the draft plans, one card each, with a count; Open → goes to the tab behind it
5Load against capacity and the other cardsLoad per team and iteration (red over capacity, amber above focus, green within, grey not set), then features at risk, cross-team dependencies, open ART risks, Scrum of Scrums issues, draft objectives and ART readiness
6The questionsOne card per question with shared notes. Edit changes the list for this session only
7FocusOne question on the screen at a time, with a timer
8Question stateDiscussed, Not discussed or Parked
9Decisions and actionsEverything recorded, filtered by kind with a count per kind
10RecordOpens the drawer to record a decision or action (section 5)
11A scope changeThe feature, its team, the effect (here Postpone), the detail, the owner, the question it came from and its status
12The team's answerOn Day 2 the feature's team answers Accept and apply or Adjusted by hand; shown here before anyone has answered

What the day tells us​

CardWhat it countsTone
Load against capacityTeam-iteration cells over capacity; names them under the gridRed when any is over
Features at riskFeatures with no team, or with half or more of their stories still in the backlog. Each has Postpone, Remove from PI and Move to team buttons that open a pre-filled scope changeAmber
Cross-team dependenciesDependencies still waiting for an answer, plus declined onesRed when any is declined
Open ART risksOpen risks at ART levelRed when one is high impact
Scrum of Scrums issuesIssues the RTE has not marked addressedRed
Draft objectivesTeams with no committed objective yet; lists each team's committed count and business valueAmber
ART readinessNeeded readiness items still openAmber

4. Working through the questions​

The session reads the project's questions (Project settings → PI Planning → Management review) live: a change to the project's list reaches every session that has not saved a list of its own. The built-in list has ten, from What insights have we gained so far? to Are there any feedback or concerns raised by stakeholders that need addressing?

  1. Type the room's notes in a question's editor. They save as you type; leaving mid-sentence keeps what was typed.
  2. Press Discussed when the room is done with it, or Park to come back later. Re-open returns it to Not discussed.
  3. + Decision under a question opens the record drawer already linked to that question; the card counts its decisions.
  4. Edit rewords, reorders or removes questions for this session; Add a question adds a line (placeholder A question management answers…) and the bin icon (Remove the question) takes one out. A list holds up to 30 questions of up to 300 characters each. Once saved, the session keeps its own list and changes to the project's list no longer reach it. The project's list (PI Planning settings) is not changed.

Focus: one question at a time​

Focus shows one question large, with Question 2 of 10, a timer for the time spent on it, its notes and Decisions from this question. Previous, Park it and Discussed — next move through the list; the last question's button reads Discussed and leaves focus. Use it on the shared screen in the room, so management talks about one thing at a time and sees how long it has taken.

note

Focus is shown on your own screen only. Unlike Present on Draft plan review, Planning adjustments and Final plan review, it is not shared with the session — the other managers keep their own view of the list. Shared presentations are described on Agenda.

Figure 2 — Focus mode: the question about removing or postponing features, two seconds in.
#ElementWhat it does
1All questionsLeaves focus and goes back to the full list
2Position and timerQuestion N of M, and the time spent on this question. The timer restarts when you move to another question
3PreviousGoes to the question before; greyed out on the first
4Park itMarks the question Parked to come back to later. You stay on it until you move
5Discussed — nextMarks it Discussed and moves to the next question. On the last question it reads Discussed and leaves focus
6Notes and decisionsThe room's notes for this question (they save as you type), and the decisions and actions linked to it, counted in the heading
7Record a decisionOpens the record drawer (section 5) linked to this question, with the kind already chosen where the question suggests one: a scope change for removing or postponing features, a risk for the risk question, a resource need for the resources question, otherwise a decision

5. Recording a decision or action​

Figure 3 — Recording a decision or action. The fields below the kind change with the kind.
  1. Press Record (or + Decision under a question, or a button on a feature at risk).
  2. Pick What it is. Hover a kind for what it means.
  3. Fill the fields for that kind, the one line, and the details.
  4. Pick an Owner and a Due time if they matter; link it to a question.
  5. Press Record. Each entry then has a status picker — To do, Doing, Done — and can be edited or removed (a scope change the team has already answered can no longer be removed).
KindMeansExtra fields
Business priorityA change to what matters most to the business this PI — presented first on Day 2—
DecisionSomething management decided—
ActionSomething someone does before Day 2 starts—
Scope changeA feature is kept, postponed, removed from the PI or moved to another teamFeature, What happens to it, and To team for a move
Vision changeA change to the vision or the goals—
Team / role changeA change to a team or its rolesOptional realignment: From team, To team, Person who moves with Share of time there, Stories that move
Resource needPeople, money or tools needed—
RiskRaised at ART level on the Risks tab at onceImpact, and Team or Programme level

Field reference​

FieldControlRequiredValidationWhere the values come from
What it isOne button per kindYes, defaults to Decision—The fixed list above
In one line (The risk for a risk)TextYes — Record stays greyed out without itUp to 300 charactersTyped
DetailsText areaNoUp to 4,000 charactersTyped
FeatureSearchable pickerYes, for a scope change—The PI's features, each with the team that plans it
What happens to itFour choicesYes, for a scope change—Keep (stays as planned), Postpone (its stories leave the iterations, back to the team's backlog), Remove from PI (the feature leaves the PI and the team's board), Move to team (another team plans it)
To teamPickerYes, for a moveNot the feature's own teamThe session's teams
From team / To team (realignment)PickersTo team is required once a From team is setMust differThe session's teams
Person who moves, Share of time therePickersNo—The From team's members; As in their own team, 25 %, 50 %, 75 % or 100 %
Stories that moveSearchable picker, adds one at a timeNo—The From team's board
Impact, Team (risk)PickersNo—Low / Medium / High; Programme level or a team
OwnerSearchable pickerNo — Nobody yet—The session's participants
DueDate and timeNo—Defaults to the start of Day 2
From the questionPickerNo — None—This session's questions

6. Sharing with the train​

  1. Press Share with the train.
  2. The drawer lists What the train reads — every entry with its kind, and for a scope change the feature and its effect. With nothing recorded it reads No changes: the teams carry on with their draft plans.
  3. Choose Ring every participant's bell (on by default) and Also send it by e-mail (off by default).
  4. Press Share. Every participant sees the review from now on; a summary is pinned on the Discussion tab.
Figure 4 — Sharing the review with the train: the summary, the bell and the e-mail switch.
#ElementWhat it does
1What the train readsThe summary every participant reads: each scope change, business priority, decision, resource need and other entry, with its kind in bold
2Ring every participant's bellSends a notification to everyone in the session. On by default
3Also send it by e-mailAlso e-mails the summary. Off by default
4ShareShares the review: the summary is pinned on Discussion, every participant can open this tab, and the review is presented on Planning adjustments on Day 2. Cancel closes the drawer without sharing

The chip changes to Shared with the time and your name. If you record more afterwards, Share again sends a fresh summary.


7. The teams' answers on Day 2​

A shared scope change, or a team / role change that moves people or stories, waits for the team it touches — Waiting for Phoenix. The team answers in the Adjust tab of its board's panel, on the Planning adjustments tab, or on the card here:

  • Accept and apply asks for confirmation (Accept and apply?, for example The stories of "Offline mode" leave the iterations and go back to the backlog.) and then Orbit makes the change on the boards: postponed stories go back to the team's backlog, a removed feature leaves the PI and the board, a moved feature goes to the other team's board, a person moves with their capacity, stories move to the other board.
  • Adjusted by hand records that the team changed its plan itself.

The answer shows as Applied or Adjusted by hand with who answered. Answering is open to the feature's team — its product owner, whoever picks its features, or anyone with the Plan right on its board — and to the RTE. See Planning adjustments.

Undoing an answer​

An answer can be taken back while the session is open (not yet committed or closed). The Undo icon sits next to the answer's chip — here, on the Planning adjustments cards and in the Adjust tab of the team board's panel — and is shown only to those who may answer the decision: the RTE, or the team (or, for a realignment, either team) the decision waits for.

Figure 5 — An answered decision with its Undo icon.
#ElementWhat it does
1Applied · Priya SharmaThe team's answer and who gave it (Adjusted by hand · name for the other answer)
2UndoTakes the answer back after a confirmation; shown to whoever may answer the decision while the session is open
Figure 6 — Undo asks first and says what it puts back.
  1. Press the Undo icon. Its tooltip reads Undo — put the applied change back and answer again (for Applied) or Undo — take "Adjusted by hand" back and answer again.
  2. Confirm in Undo this answer? with Undo.
  3. The toast Answer undone confirms it; the decision shows Waiting for Phoenix again and returns to the status it had before the answer.
The answer wasWhat Undo puts back
AppliedWhat Accept and apply changed: postponed stories go back to the iteration they left (a story planned somewhere else since then stays where it is); a moved or removed feature returns to its team and to the PI's scope; a realigned person and the moved stories go back to the team they came from
Adjusted by handNothing on the boards changes; only the answer is cleared

Everyone in the session sees the decision waiting again at once, on this tab, on Planning adjustments and on the team's board. An answer applied before Undo was available in your workspace has nothing recorded to put back: the icon is not shown for it, and the board is changed by hand instead.

ElementControlWho sees itWhat it does
Undo iconIcon button beside Applied · name or Adjusted by hand · nameThe RTE and the team(s) the decision waits for, while the session is openOpens Undo this answer?; on Undo the answer is cleared and an applied change is put back

8. Worked example: Day 1, 17:00​

Maya Fernandes closes the Draft plan review and opens the management review with Lena Hoffmann, Kenji Watanabe, Sofia Alvarez and David Okafor.

  1. What the day tells us. Load shows Phoenix at 110 % in Iteration 1 (red); Atlas's cells are green. Two cross-team dependencies wait for an answer, one ART risk is open, Scrum of Scrums has one issue — Atlas on dependencies.
  2. Question 1, What insights have we gained so far? Maya types: Phoenix is over capacity in Iteration 1; Atlas carries the riskiest work (NPCI certification and the fraud model). Discussed.
  3. Question 2, on changes to vision and scope: Offline mode can wait a PI — the investor demo is about checkout and payments. Maya presses + Decision, picks Scope change, feature Offline mode — Phoenix, Postpone, one line Postpone Offline mode to PI 2027.1, detail Frees Phoenix capacity for checkout in Iterations 2 and 3.
  4. She records a Business priority — Atlas: device fingerprint signals first, owner Marco Rossi — a Decision — Tracing is the reference for checkout latency — and a Resource need: an engineer lent from Orion.
  5. Share with the train, bell on. The summary is pinned on Discussion.
  6. Day 2. Phoenix's board shows 1 management adjustment for Phoenix · 1 to answer. Priya Sharma presses Accept and apply; Offline mode's stories leave the iterations and the card reads Applied.

9. The admin contract​

Must be in placeWhereWhat happens without it
The ART roles named on the session — Product Manager, System Architect, Business OwnersThe session's setup (Create a session)Only the RTE and PI Planning managers can work in the review
A Draft plan review agenda itemThe session's agenda (Agenda)The review opens only once the session is in review
The project's question listProject settings → PI Planning → Management review (PI Planning settings)The ten default questions are used
Features given to teamsFeatures & teams (Features and teams)Every feature shows under Features at risk as having no team
Team product owners and roles with the Plan rightPlanning Teams and Roles & permissions (Roles and permissions)Only the RTE can answer a scope change
The Management review row for the ART rolesProject settings → PI Planning → Roles & permissions (Roles and permissions)Only the RTE writes the review; the other managers read it once it is shared

10. Downstream effects​

  • A Risk entry is placed on the session's Risks tab at ART level straight away, shared or not.
  • Sharing makes the review visible to every participant, pins a summary on Discussion, and adds the Adjust tab to each team board's panel.
  • Accept and apply changes the team boards; those changes reach the tasks at merge & commit.
  • The decisions are presented on Day 2 on Planning adjustments, business priorities first.

11. Don't confuse this with…​

  • The draft plan review — the teams present; nothing is decided. See Draft plan review.
  • Planning adjustments — Day 2's presentation of these decisions and the teams' questions on them. See Planning adjustments.
  • Broadcast — the facilitator's free-text message to everyone. Sharing the review pins its own summary.
  • The final plan review — Day 2's decision to accept each team's plan or send it back. See Final plan review.

12. Troubleshooting​

What you seeWhyWhat to do
Management has not shared its review yetYou are not on the management team and it is not sharedWait for the RTE to share it
The tab is locked for managementThe Draft plan review item has not been closedThe facilitator closes it
Record stays greyed outThe one line is empty, or a scope change lacks its feature, effect or target teamFill the missing field
Features at risk lists every featureTheir stories still count as being in the backlogRead the team boards and the draft plan review for what each team planned
Draft objectives shows 0Every team has at least one committed objectiveExpected — the count is of teams without one
A team cannot answer a scope changeThe person lacks the Plan right on the team's board and does not pick its featuresThe product owner or the RTE answers
The remove button is gone from a scope changeThe team has already answered itRecord a new decision instead
The teams did not get an e-mailAlso send it by e-mail was offShare again with it on
A Business Owner sees Management has not shared its review yetTheir role lacks the Management review row in the rule bookAdd the row in Roles & permissions, or wait for the RTE to share
the Management review list has at most 30 questionsThe session's or project's list has more than 30 questionsMerge or remove questions, then save
a question is at most 300 charactersOne question is too longShorten it
No Undo icon next to an answerYou are not the RTE or on the team the decision waits for, or the session is committed or closedThe team's lead or the RTE undoes it
This change was applied before it could be undone — change the board by hand.The answer was applied before Undo was available, so nothing was recorded to put backMove the stories or the feature back on the board by hand
A project question change did not reach a sessionThat session saved its own list with EditChange the session's list with Edit