Post-PI Planning

What this page is — the Post-PI Planning tab: the RTE's seven-step checklist for after the event — commit the plan to the live tasks, integrate the ART PI objectives, keep the ROAM record and the ART Planning Board, set up the recurring ART events, close the retrospective and start the next PI Planning.

What it is for — making sure the outputs of two days of planning leave the room and become the way the train works for the next ten weeks, not a board that nobody opens again.

The problem it solves — teams leave the event with their own plans, but the ART's outputs stay with the RTE: the plan still lives only on the PI boards, the ART objectives are unwritten, the risk decisions sit in the session and nobody has booked the system demos. A week later the tasks in the project still show the old iterations and the first iteration planning starts from the wrong backlog.

Route: /org/tasks/pi-planning?session=…&tab=post_pi · Who sees it: the session's named facilitator (the RTE); other roles only if the project's Roles & permissions rule book gives them the tab · To merge and commit: be the session's named facilitator, and hold Create and edit scenarios, move and assign tasks on the board, edit capacity and goals, manage planned hires, and commit a scenario to real tasks.


1. The checklist​

The tab opens with After the PI Planning event and a reminder of what the RTE owns, then seven steps. Each step has its own tool and a tick. Four of them tick themselves when the data shows the work is done; the others are ticked by hand.

#StepTicks itself whenTool in the step
1Commit the planThe plan is committedMerge & commit drawer
2Integrated ART PI objectivesThere is at least one ART objective and every committed team objective rolls up into oneWrite ART objectives, roll team objectives up
3Capture the ROAM decisions— (by hand)The ART risks with ROAM state; export, pin
4Keep the ART Planning Board for the PI— (by hand)Opens the ART Planning Board
5Set up the recurring ART eventsEvents have been createdEvent table, calendar picker, .ics download
6Close the retrospectiveA closing time is setThe retrospective's closing controls
7Start planning the next PI PlanningYou press its buttonStart the next PI Planning
Post-PI PlanningThe session's other tabs
WhoThe RTE, or roles the rule book gives the tabEveryone in the session
WhenFrom the moment the session is published, used after the eventDuring the event
Writes to live tasksYes — step 1No
Other modulesOrbit Schedule (step 5)None

2. Why you would use it​

  • The plan becomes the work. One commit writes every story's iteration and assignee, the accepted cross-team dependencies and the iteration goals to the project's tasks — reviewed change by change first, like any Planning commit.
  • Management gets one story, not three. The ART PI objectives summarise the teams' objectives, with each team objective's business value beside it.
  • Risk decisions do not get lost. The ROAM record exports to a spreadsheet and pins to the Discussion tab where everyone can find it.
  • The PI's rhythm is booked in one go. Nineteen events for a three-iteration PI — iteration planning, system demos, syncs and Inspect & Adapt — created with the train invited, instead of an afternoon of calendar work.
  • The next event starts warm. A new session inherits this one's teams, roles, measure and agenda.

3. Who sees it and when​

  • The tab is visible once the session is published. By default it is the RTE's only: even someone holding Create, edit and close PI sessions, choose the participating teams, and edit the project's PI Planning settings. does not see it unless the rule book gives their role the tab.
  • A participant's rail (for example Arjun Rao's) has no Post-PI Planning entry.
  • The Merge & commit button in the session bar opens this tab with the merge drawer.

4. Step 1 and step 2 — commit, and ART objectives​

Figure 1 — Steps 1 and 2: commit the plan, and the integrated ART PI objectives.
#ElementWhat it does
1After the PI Planning eventThe RTE's checklist; only the RTE, or roles given the tab, see it
2Step 1 — Commit the planWrites the plan to the live tasks
3Merge the team plansMerges every team's board into one plan and opens the Merge & commit the PI plan drawer
4Mark doneTicks a step by hand. A ticked step shows Done · name and Undo
5Step 2 — Integrated ART PI objectivesThe synthesis of the teams' PI objectives, for management and to track progress. The committed ones are the PI's goal, whether written before or after the commit
6New ART objectiveType it, choose Committed or Stretch, press Add
7Every committed team objective rolls upThe step ticks itself when no committed team objective is left over
8An ART objectiveLists the team objectives rolled up into it, each with its business value

Commit the plan​

  1. Make sure the session is in Review. After a plan rework the session is in Adjusting; start a review item on the agenda to move it back. In any other status the card reads Available in review.
  2. Write the ART objectives (step 2) — before or after the commit, see the note below.
  3. Press Merge the team plans. A message Team plans merged confirms how many tasks from how many teams.
  4. Review the drawer (Figure 4), then press Commit the PI plan.
ART objectives before or after the commit

Merging copies the committed ART objectives into the PI's goal, and the committed team objectives (with their business value) into its success criteria. Once the plan is committed, the RTE can still add, edit or remove ART objectives in step 2: each change rewrites the PI's goal and success criteria the same way, at once. The step's hint says so: The committed ones are the PI's goal — before or after the commit.

Integrate the ART PI objectives​

  1. Type an objective in An ART PI objective, e.g. Deliver basic shopping cart… (up to 300 characters). Click Committed to switch it to Stretch if it is uncommitted.
  2. Press Add.
  3. For each team objective on the right, pick the ART objective it rolls up into, or Not rolled up. Its business value (BV) shows beside it.
  4. A warning counts committed team objectives not rolled up yet until none is left; the step then ticks itself.
  5. Remove an ART objective with the bin icon and confirm; its team objectives stop rolling up.
  6. On a committed session, each add, edit or removal also updates the PI's goal in Planning straight away.

Business value stays on the team objectives; ART objectives have none.


5. Steps 3 to 5 — ROAM record, ART board, ART events​

Figure 2 — The ROAM record, the ART Planning Board and the start of the ART events.
#ElementWhat it does
1Step 3 — the ROAM recordEach ART risk with its ROAM state, team (or Programme), owner and note
2Export (CSV)Downloads the record: Risk, Team, ROAM, Owner, Note, Impact
3Pin the record on DiscussionPosts the record on the Discussion tab and pins it, without a bell or an email
4A ticked stepShows Done · Maya Fernandes; Undo un-ticks it
5Step 4 — Keep the ART Planning Board for the PIThe board stays in the session, read-only once committed, for dependency and milestone management
6Step 5 — Set up the recurring ART eventsWorked out from the PI's iterations
7An event rowSwitch it on or off, set its time and minutes; How many is computed

Step 3. If any ART risk is still Open, the step warns how many and points to the Risks tab (Open ART Risks →). Only ART-level and programme-level risks are listed; team risks stay with the teams. Tick the step when every risk has an owner who manages it through the PI.

Step 4. Open the ART Planning Board takes you to the ART Planning Board. Tick the step once you have agreed who keeps it current.

Figure 3 — The ART events, the retrospective's closing and the next PI Planning.
#ElementWhat it does
1Step 6 — Close the retrospectiveThe retrospective's closing time, and how many notes it holds
2Leave it open for … hours · Close nowLeave it open for some hours (it then closes by itself) or close it now
3Step 7 — Start planning the next PI PlanningThe next event
4Start the next PI PlanningOpens the session setup for a new session seeded from this one's teams, roles, measure and agenda

Step 5 — the events.

EventDefault timeMinutesWhen
Iteration planning09:00120The first day of every iteration
System demo15:0060The last day of every iteration
ART sync10:0060Every Wednesday of the PI
PO sync11:0030Every Thursday of the PI
Inspect & Adapt13:00180The last day of the PI
  1. Switch off the events you do not want; change times and minutes (15 to 480, in steps of 15). How many updates as you go.
  2. Pick a calendar in Pick an Orbit Schedule calendar…. Only the project's active calendars are listed.
  3. Press Create N events in Orbit Schedule and confirm. Everyone in the session — team members, the RTE, the Product Manager, the System Architect and the Business Owners — is invited and gets a bell. Anyone who cannot see that calendar is left off the invitation.
  4. A message confirms how many events were created (N ART events created — The train is invited…); the step ticks itself.
  5. Pressing the button again — or from a second tab at the same time — never makes an event twice. The confirmation says how many were created already — those are not made again; only the missing ones are created, and the message adds M were there already and were not made again. When all of them exist, the message is Nothing new to create — All N events are on the calendar already. An event is the same event when its kind and start time match; one that failed to be created is created when you press again.
  6. Or press Download (.ics) for a calendar file to import anywhere.

Step 6. The same controls as on the Retrospective tab. Setting a closing time ticks the step.

Step 7. Pressing Start the next PI Planning ticks the step and opens the new-session setup, where you pick the next PI and its dates.


6. Field reference and the merge & commit drawer​

Field or controlStepTypeRules
New ART objective2One-line textRequired to add; up to 300 characters
Committed / Stretch2ToggleCommitted by default; only committed ART objectives reach the PI's goal
Roll-up picker2Drop-downNot rolled up or one of the session's ART objectives
Event switch5SwitchAll five on by default
Event time5TimeLocal time of your browser
Event minutes5Number15 to 480, in steps of 15
Calendar5Drop-downThe project's active Orbit Schedule calendars
Leave it open for6Number, hours1 to 336
WriteDrawerTick per taskAll ticked; an unticked task is left out of this commit
Commit despite the warningsDrawerTickShown only when there are warnings; required to commit then
Figure 4 — The merged plan, reviewed change by change before it is committed.
#ElementWhat it does
1Teams · Tasks in the planHow many team boards were merged and how many tasks the merged plan holds
2Tasks changingHow many tasks the commit changes
3Cross-team linksAccepted cross-team dependencies that become task dependencies
4Committed hoursPlanned hours against the train's net capacity
5Task changesEvery change — task, field, from, to — reviewed like any Planning commit
6WriteUntick a task to leave it out of this commit
7Commit the PI planWrites the plan to the live tasks. Warnings, if any, must be acknowledged first

What else the drawer can show:

SectionMeaningWhat you do
N problems block the commit (red)Something the commit cannot writeFix it on the team boards, then merge again
N warnings (amber)Load warnings in the session's measure (see below), and other warnings of a Planning commitTick Commit despite the warnings to go ahead
Shared peoplePeople in more than one team: one capacity, every team's loadCheck their load
N dependencies will be added to the tasksLinks that become task dependencies—
GoalsEach iteration's new goal—

Load warnings, in the session's measure. The drawer checks the load the way the session counts it:

Session measureWhat is checkedWarnings
Story points or valueEach team, in each iteration, against that team's own capacity for the iterationA team is planned above its capacity in an iteration. or A team is planned below the underload ratio of its capacity in an iteration., with the detail, for example Phoenix · Iteration 1: 12 SP of 30 SP (a value session reads the amount and currency, such as 1200 EUR). An iteration with no capacity set is not checked
DaysEach person, as in a Planning commitRead in days, for example 3.5d of 10d
HoursEach person, as in a Planning commitRead in hours

The underload ratio is the project's Planning setting (60 % unless changed). Commit the PI plan asks you to acknowledge the same warnings the merge showed.

The footer says what stands in the way: Committing also needs the Planning — "Create and edit scenarios, … and commit a scenario to real tasks" permission — ask someone who has it. (the line names the permission as the role editor shows it, followed by its code in brackets), Tick "Commit despite the warnings" to go ahead., how many tasks are left out, or Ready to commit.

Exactly what reaches the live tasks​

Written to the projectFrom
Each task's iteration (time box), assignee, size and other planned fields shown in Task changesThe team boards; for a task on two boards, the team chosen when the conflict was decided
Tasks created on a team boardCreated as real tasks
Task dependenciesEach team's own links and every accepted cross-team dependency
Each iteration's goalThe teams' goals for it, joined as Team: goal · Team: goal; an iteration no team set a goal for keeps its own
The PI's goalThe committed ART objectives, joined
The PI's success criteriaThe committed team objectives, as Team: objective (BV n)

Stretch objectives, risks, retrospective notes and the confidence vote are not written to tasks.

After a full commit the session becomes Committed, the boards turn read-only, step 1 shows Committed, and everyone is notified once. If you untick tasks, the commit writes the rest and the session stays in Review: the unticked tasks stay planned and can be committed later by merging and committing again. If the plan changed in the meantime (a live task edited, another commit), the drawer merges again and shows the new review instead of committing.


7. Worked example — PI 2026.4​

  1. After the round-2 vote and the retrospective, Maya Fernandes starts a review item; the session is Review · Planning round 3 and the agenda reads Agenda complete.
  2. In step 2 she adds the committed ART objective Shoppers pay in one tap on any network — card or UPI — for the investor demo and rolls up six team objectives — Phoenix's Shoppers pay with a saved card in one tap (BV 10) and Wallet payments on iOS and Android (7), Atlas's two (9 and 8) and Orion's two (6 and 5). The stretch objectives stay Not rolled up; the step ticks itself.
  3. She presses Merge the team plans: 3 teams, 21 tasks, 20 changing, 2 cross-team links, 486h / 1072h. The session counts in story points, so the warnings read per team and iteration — among them Phoenix · Iteration 1: 11 SP of 10 SP (above its capacity) and Phoenix · Iteration 3: 2 SP of 20 SP (below the 60 % underload ratio), the load the Business Owners accepted in the final plan review. She ticks Commit despite the warnings; the footer reads Ready to commit. She presses Commit the PI plan.
  4. Step 3 lists NPCI (Owned, Marco Rossi), Apple Pay approval (Mitigated) and the code freeze (Accepted). She exports the CSV and pins the record on Discussion, then ticks the step. She ticks step 4 once the train has agreed who keeps the ART board current.
  5. Step 5 counts 3 + 3 + 6 + 6 + 1 = 19 events from Iterations 1–3 (5 Oct – 13 Nov). She picks the project's calendar and presses Create 19 events in Orbit Schedule. Unsure whether it worked, she presses it again an hour later: Nothing new to create — All 19 events are on the calendar already.
  6. A week later Lena Hoffmann asks for a sharper ART objective. Maya edits it in step 2; the PI's goal in Planning changes with it, although the plan is already committed.
  7. She sets the retrospective to stay open 24 hours, and finally presses Start the next PI Planning.

8. The admin contract​

Must be in placeWhereWhat breaks without it
A named facilitatorThe sessionNobody sees the tab unless the rule book opens it
The tab for other roles, if wantedRoles & permissionsOnly the RTE sees it
The RTE holds Create and edit scenarios, … and commit a scenario to real tasks.Role editorMerging works; Commit the PI plan stays greyed out
Every cross-team task conflict decidedART Planning BoardMerging stops until each conflict has a winning team
The session's PI and iterationsCreate a sessionNo PI goal is written, and step 5 computes no events
An active calendar in Orbit Schedule, and the right to create events in itOrbit ScheduleStep 5 offers only the .ics download, or reports that some events could not be created

9. What it changes elsewhere​

  • The PI's goal — set by the merge, and rewritten whenever an ART objective changes after the commit.
  • Project tasks and Planning — the commit appears in the project's Planning commit history like any other commit, and the tasks show their new iterations, assignees and dependencies.
  • Orbit Schedule — the ART events on the chosen calendar, with the train invited. Creating again adds only the events that are missing; an event already created is never made twice.
  • Discussion — the pinned ROAM record.
  • PI Planning — a new session from step 7.

10. Don't confuse this with…​

ThisIs notBecause
ART PI objectivesTeam objectives on the Objectives tabTeams write theirs with business value; the RTE writes the ART's as a summary, without business value
Committing hereCommitting a scenario in PlanningIt uses the same review and commit, but for one merged plan of every team at once
The ROAM recordThe Risks tabThe record is a read-out of the ART risks for after the event; risks are still changed on the Risks tab
Step 7Copying the sessionIt starts a new session from this one's set-up, not its plan

11. Troubleshooting​

SymptomCauseWhat to do
The tab is missing from the railYou are not the RTE and the rule book does not give your role the tabAsk the RTE, or a project manager to change the rule book
Available in review. instead of the merge buttonThe session is not in Review (for example Adjusting after a rework)Start a review item on the agenda
Merging fails with a conflict messageA task on two teams' boards has no winning teamDecide the conflict, then merge again
Commit the PI plan greyed outBlocking problems, unacknowledged warnings, or the Planning commit permission missingRead the footer line and act on it
The drawer re-opened with a new review after commitThe plan changed after the reviewReview the new changes and commit again
The session stayed in Review after committingSome tasks were untickedMerge and commit again to write them, or leave them planned
The PI goal in Planning lacks the ART objectiveIt is a Stretch objective; only committed ART objectives reach the goalSwitch it to Committed in step 2
No calendar to pickThe project has no active Orbit Schedule calendar, or you cannot open its calendarsCreate one in Orbit Schedule, or use Download (.ics)
Nothing new to createEvery event in the table is on the calendar alreadyNothing; change an event's time or switch one on to create something new
A second set of events after changing the timesAn event with a new start time is a new eventDelete the ones you do not want in Orbit Schedule
N of M events created (error)Some events could not be created, for example you may not create events on that calendarCheck your rights in Orbit Schedule and press Create again: only the missing events are made
Load warnings in story points instead of hoursThe session counts in story points, so the merge checks each team's load per iteration against its capacityCompare with the team's capacity for that iteration, or tick Commit despite the warnings
Committing also needs the Planning — … permissionYour role lacks the Planning permission that commits scenarios to real tasksAsk someone who holds it, or an administrator to grant it