Post-PI Planning
What this page is — the Post-PI Planning tab: the RTE's seven-step checklist for after the event — commit the plan to the live tasks, integrate the ART PI objectives, keep the ROAM record and the ART Planning Board, set up the recurring ART events, close the retrospective and start the next PI Planning.
What it is for — making sure the outputs of two days of planning leave the room and become the way the train works for the next ten weeks, not a board that nobody opens again.
The problem it solves — teams leave the event with their own plans, but the ART's outputs stay with the RTE: the plan still lives only on the PI boards, the ART objectives are unwritten, the risk decisions sit in the session and nobody has booked the system demos. A week later the tasks in the project still show the old iterations and the first iteration planning starts from the wrong backlog.
Route: /org/tasks/pi-planning?session=…&tab=post_pi · Who sees it: the session's named
facilitator (the RTE); other roles only if the project's Roles & permissions
rule book gives them the tab · To merge and commit: be the session's named facilitator, and hold
Create and edit scenarios, move and assign tasks on the board, edit capacity and goals, manage
planned hires, and commit a scenario to real tasks.
1. The checklist
The tab opens with After the PI Planning event and a reminder of what the RTE owns, then seven steps. Each step has its own tool and a tick. Four of them tick themselves when the data shows the work is done; the others are ticked by hand.
| # | Step | Ticks itself when | Tool in the step |
|---|---|---|---|
| 1 | Commit the plan | The plan is committed | Merge & commit drawer |
| 2 | Integrated ART PI objectives | There is at least one ART objective and every committed team objective rolls up into one | Write ART objectives, roll team objectives up |
| 3 | Capture the ROAM decisions | — (by hand) | The ART risks with ROAM state; export, pin |
| 4 | Keep the ART Planning Board for the PI | — (by hand) | Opens the ART Planning Board |
| 5 | Set up the recurring ART events | Events have been created | Event table, calendar picker, .ics download |
| 6 | Close the retrospective | A closing time is set | The retrospective's closing controls |
| 7 | Start planning the next PI Planning | You press its button | Start the next PI Planning |
| Post-PI Planning | The session's other tabs | |
|---|---|---|
| Who | The RTE, or roles the rule book gives the tab | Everyone in the session |
| When | From the moment the session is published, used after the event | During the event |
| Writes to live tasks | Yes — step 1 | No |
| Other modules | Orbit Schedule (step 5) | None |
2. Why you would use it
- The plan becomes the work. One commit writes every story's iteration and assignee, the accepted cross-team dependencies and the iteration goals to the project's tasks — reviewed change by change first, like any Planning commit.
- Management gets one story, not three. The ART PI objectives summarise the teams' objectives, with each team objective's business value beside it.
- Risk decisions do not get lost. The ROAM record exports to a spreadsheet and pins to the Discussion tab where everyone can find it.
- The PI's rhythm is booked in one go. Nineteen events for a three-iteration PI — iteration planning, system demos, syncs and Inspect & Adapt — created with the train invited, instead of an afternoon of calendar work.
- The next event starts warm. A new session inherits this one's teams, roles, measure and agenda.
3. Who sees it and when
- The tab is visible once the session is published. By default it is the RTE's only: even someone holding Create, edit and close PI sessions, choose the participating teams, and edit the project's PI Planning settings. does not see it unless the rule book gives their role the tab.
- A participant's rail (for example Arjun Rao's) has no Post-PI Planning entry.
- The Merge & commit button in the session bar opens this tab with the merge drawer.
4. Step 1 and step 2 — commit, and ART objectives
| # | Element | What it does |
|---|---|---|
| 1 | After the PI Planning event | The RTE's checklist; only the RTE, or roles given the tab, see it |
| 2 | Step 1 — Commit the plan | Writes the plan to the live tasks |
| 3 | Merge the team plans | Merges every team's board into one plan and opens the Merge & commit the PI plan drawer |
| 4 | Mark done | Ticks a step by hand. A ticked step shows Done · name and Undo |
| 5 | Step 2 — Integrated ART PI objectives | The synthesis of the teams' PI objectives, for management and to track progress. The committed ones are the PI's goal, whether written before or after the commit |
| 6 | New ART objective | Type it, choose Committed or Stretch, press Add |
| 7 | Every committed team objective rolls up | The step ticks itself when no committed team objective is left over |
| 8 | An ART objective | Lists the team objectives rolled up into it, each with its business value |
Commit the plan
- Make sure the session is in Review. After a plan rework the session is in Adjusting; start a review item on the agenda to move it back. In any other status the card reads Available in review.
- Write the ART objectives (step 2) — before or after the commit, see the note below.
- Press Merge the team plans. A message Team plans merged confirms how many tasks from how many teams.
- Review the drawer (Figure 4), then press Commit the PI plan.
Merging copies the committed ART objectives into the PI's goal, and the committed team objectives (with their business value) into its success criteria. Once the plan is committed, the RTE can still add, edit or remove ART objectives in step 2: each change rewrites the PI's goal and success criteria the same way, at once. The step's hint says so: The committed ones are the PI's goal — before or after the commit.
Integrate the ART PI objectives
- Type an objective in An ART PI objective, e.g. Deliver basic shopping cart… (up to 300 characters). Click Committed to switch it to Stretch if it is uncommitted.
- Press Add.
- For each team objective on the right, pick the ART objective it rolls up into, or Not rolled up. Its business value (BV) shows beside it.
- A warning counts committed team objectives not rolled up yet until none is left; the step then ticks itself.
- Remove an ART objective with the bin icon and confirm; its team objectives stop rolling up.
- On a committed session, each add, edit or removal also updates the PI's goal in Planning straight away.
Business value stays on the team objectives; ART objectives have none.
5. Steps 3 to 5 — ROAM record, ART board, ART events
| # | Element | What it does |
|---|---|---|
| 1 | Step 3 — the ROAM record | Each ART risk with its ROAM state, team (or Programme), owner and note |
| 2 | Export (CSV) | Downloads the record: Risk, Team, ROAM, Owner, Note, Impact |
| 3 | Pin the record on Discussion | Posts the record on the Discussion tab and pins it, without a bell or an email |
| 4 | A ticked step | Shows Done · Maya Fernandes; Undo un-ticks it |
| 5 | Step 4 — Keep the ART Planning Board for the PI | The board stays in the session, read-only once committed, for dependency and milestone management |
| 6 | Step 5 — Set up the recurring ART events | Worked out from the PI's iterations |
| 7 | An event row | Switch it on or off, set its time and minutes; How many is computed |
Step 3. If any ART risk is still Open, the step warns how many and points to the Risks tab (Open ART Risks →). Only ART-level and programme-level risks are listed; team risks stay with the teams. Tick the step when every risk has an owner who manages it through the PI.
Step 4. Open the ART Planning Board takes you to the ART Planning Board. Tick the step once you have agreed who keeps it current.
| # | Element | What it does |
|---|---|---|
| 1 | Step 6 — Close the retrospective | The retrospective's closing time, and how many notes it holds |
| 2 | Leave it open for … hours · Close now | Leave it open for some hours (it then closes by itself) or close it now |
| 3 | Step 7 — Start planning the next PI Planning | The next event |
| 4 | Start the next PI Planning | Opens the session setup for a new session seeded from this one's teams, roles, measure and agenda |
Step 5 — the events.
| Event | Default time | Minutes | When |
|---|---|---|---|
| Iteration planning | 09:00 | 120 | The first day of every iteration |
| System demo | 15:00 | 60 | The last day of every iteration |
| ART sync | 10:00 | 60 | Every Wednesday of the PI |
| PO sync | 11:00 | 30 | Every Thursday of the PI |
| Inspect & Adapt | 13:00 | 180 | The last day of the PI |
- Switch off the events you do not want; change times and minutes (15 to 480, in steps of 15). How many updates as you go.
- Pick a calendar in Pick an Orbit Schedule calendar…. Only the project's active calendars are listed.
- Press Create N events in Orbit Schedule and confirm. Everyone in the session — team members, the RTE, the Product Manager, the System Architect and the Business Owners — is invited and gets a bell. Anyone who cannot see that calendar is left off the invitation.
- A message confirms how many events were created (N ART events created — The train is invited…); the step ticks itself.
- Pressing the button again — or from a second tab at the same time — never makes an event twice. The confirmation says how many were created already — those are not made again; only the missing ones are created, and the message adds M were there already and were not made again. When all of them exist, the message is Nothing new to create — All N events are on the calendar already. An event is the same event when its kind and start time match; one that failed to be created is created when you press again.
- Or press Download (.ics) for a calendar file to import anywhere.
Step 6. The same controls as on the Retrospective tab. Setting a closing time ticks the step.
Step 7. Pressing Start the next PI Planning ticks the step and opens the new-session setup, where you pick the next PI and its dates.
6. Field reference and the merge & commit drawer
| Field or control | Step | Type | Rules |
|---|---|---|---|
| New ART objective | 2 | One-line text | Required to add; up to 300 characters |
| Committed / Stretch | 2 | Toggle | Committed by default; only committed ART objectives reach the PI's goal |
| Roll-up picker | 2 | Drop-down | Not rolled up or one of the session's ART objectives |
| Event switch | 5 | Switch | All five on by default |
| Event time | 5 | Time | Local time of your browser |
| Event minutes | 5 | Number | 15 to 480, in steps of 15 |
| Calendar | 5 | Drop-down | The project's active Orbit Schedule calendars |
| Leave it open for | 6 | Number, hours | 1 to 336 |
| Write | Drawer | Tick per task | All ticked; an unticked task is left out of this commit |
| Commit despite the warnings | Drawer | Tick | Shown only when there are warnings; required to commit then |
| # | Element | What it does |
|---|---|---|
| 1 | Teams · Tasks in the plan | How many team boards were merged and how many tasks the merged plan holds |
| 2 | Tasks changing | How many tasks the commit changes |
| 3 | Cross-team links | Accepted cross-team dependencies that become task dependencies |
| 4 | Committed hours | Planned hours against the train's net capacity |
| 5 | Task changes | Every change — task, field, from, to — reviewed like any Planning commit |
| 6 | Write | Untick a task to leave it out of this commit |
| 7 | Commit the PI plan | Writes the plan to the live tasks. Warnings, if any, must be acknowledged first |
What else the drawer can show:
| Section | Meaning | What you do |
|---|---|---|
| N problems block the commit (red) | Something the commit cannot write | Fix it on the team boards, then merge again |
| N warnings (amber) | Load warnings in the session's measure (see below), and other warnings of a Planning commit | Tick Commit despite the warnings to go ahead |
| Shared people | People in more than one team: one capacity, every team's load | Check their load |
| N dependencies will be added to the tasks | Links that become task dependencies | — |
| Goals | Each iteration's new goal | — |
Load warnings, in the session's measure. The drawer checks the load the way the session counts it:
| Session measure | What is checked | Warnings |
|---|---|---|
| Story points or value | Each team, in each iteration, against that team's own capacity for the iteration | A team is planned above its capacity in an iteration. or A team is planned below the underload ratio of its capacity in an iteration., with the detail, for example Phoenix · Iteration 1: 12 SP of 30 SP (a value session reads the amount and currency, such as 1200 EUR). An iteration with no capacity set is not checked |
| Days | Each person, as in a Planning commit | Read in days, for example 3.5d of 10d |
| Hours | Each person, as in a Planning commit | Read in hours |
The underload ratio is the project's Planning setting (60 % unless changed). Commit the PI plan asks you to acknowledge the same warnings the merge showed.
The footer says what stands in the way: Committing also needs the Planning — "Create and edit scenarios, … and commit a scenario to real tasks" permission — ask someone who has it. (the line names the permission as the role editor shows it, followed by its code in brackets), Tick "Commit despite the warnings" to go ahead., how many tasks are left out, or Ready to commit.
Exactly what reaches the live tasks
| Written to the project | From |
|---|---|
| Each task's iteration (time box), assignee, size and other planned fields shown in Task changes | The team boards; for a task on two boards, the team chosen when the conflict was decided |
| Tasks created on a team board | Created as real tasks |
| Task dependencies | Each team's own links and every accepted cross-team dependency |
| Each iteration's goal | The teams' goals for it, joined as Team: goal · Team: goal; an iteration no team set a goal for keeps its own |
| The PI's goal | The committed ART objectives, joined |
| The PI's success criteria | The committed team objectives, as Team: objective (BV n) |
Stretch objectives, risks, retrospective notes and the confidence vote are not written to tasks.
After a full commit the session becomes Committed, the boards turn read-only, step 1 shows Committed, and everyone is notified once. If you untick tasks, the commit writes the rest and the session stays in Review: the unticked tasks stay planned and can be committed later by merging and committing again. If the plan changed in the meantime (a live task edited, another commit), the drawer merges again and shows the new review instead of committing.
7. Worked example — PI 2026.4
- After the round-2 vote and the retrospective, Maya Fernandes starts a review item; the session is Review · Planning round 3 and the agenda reads Agenda complete.
- In step 2 she adds the committed ART objective Shoppers pay in one tap on any network — card or UPI — for the investor demo and rolls up six team objectives — Phoenix's Shoppers pay with a saved card in one tap (BV 10) and Wallet payments on iOS and Android (7), Atlas's two (9 and 8) and Orion's two (6 and 5). The stretch objectives stay Not rolled up; the step ticks itself.
- She presses Merge the team plans: 3 teams, 21 tasks, 20 changing, 2 cross-team links, 486h / 1072h. The session counts in story points, so the warnings read per team and iteration — among them Phoenix · Iteration 1: 11 SP of 10 SP (above its capacity) and Phoenix · Iteration 3: 2 SP of 20 SP (below the 60 % underload ratio), the load the Business Owners accepted in the final plan review. She ticks Commit despite the warnings; the footer reads Ready to commit. She presses Commit the PI plan.
- Step 3 lists NPCI (Owned, Marco Rossi), Apple Pay approval (Mitigated) and the code freeze (Accepted). She exports the CSV and pins the record on Discussion, then ticks the step. She ticks step 4 once the train has agreed who keeps the ART board current.
- Step 5 counts 3 + 3 + 6 + 6 + 1 = 19 events from Iterations 1–3 (5 Oct – 13 Nov). She picks the project's calendar and presses Create 19 events in Orbit Schedule. Unsure whether it worked, she presses it again an hour later: Nothing new to create — All 19 events are on the calendar already.
- A week later Lena Hoffmann asks for a sharper ART objective. Maya edits it in step 2; the PI's goal in Planning changes with it, although the plan is already committed.
- She sets the retrospective to stay open 24 hours, and finally presses Start the next PI Planning.
8. The admin contract
| Must be in place | Where | What breaks without it |
|---|---|---|
| A named facilitator | The session | Nobody sees the tab unless the rule book opens it |
| The tab for other roles, if wanted | Roles & permissions | Only the RTE sees it |
| The RTE holds Create and edit scenarios, … and commit a scenario to real tasks. | Role editor | Merging works; Commit the PI plan stays greyed out |
| Every cross-team task conflict decided | ART Planning Board | Merging stops until each conflict has a winning team |
| The session's PI and iterations | Create a session | No PI goal is written, and step 5 computes no events |
| An active calendar in Orbit Schedule, and the right to create events in it | Orbit Schedule | Step 5 offers only the .ics download, or reports that some events could not be created |
9. What it changes elsewhere
- The PI's goal — set by the merge, and rewritten whenever an ART objective changes after the commit.
- Project tasks and Planning — the commit appears in the project's Planning commit history like any other commit, and the tasks show their new iterations, assignees and dependencies.
- Orbit Schedule — the ART events on the chosen calendar, with the train invited. Creating again adds only the events that are missing; an event already created is never made twice.
- Discussion — the pinned ROAM record.
- PI Planning — a new session from step 7.
10. Don't confuse this with…
| This | Is not | Because |
|---|---|---|
| ART PI objectives | Team objectives on the Objectives tab | Teams write theirs with business value; the RTE writes the ART's as a summary, without business value |
| Committing here | Committing a scenario in Planning | It uses the same review and commit, but for one merged plan of every team at once |
| The ROAM record | The Risks tab | The record is a read-out of the ART risks for after the event; risks are still changed on the Risks tab |
| Step 7 | Copying the session | It starts a new session from this one's set-up, not its plan |
11. Troubleshooting
| Symptom | Cause | What to do |
|---|---|---|
| The tab is missing from the rail | You are not the RTE and the rule book does not give your role the tab | Ask the RTE, or a project manager to change the rule book |
| Available in review. instead of the merge button | The session is not in Review (for example Adjusting after a rework) | Start a review item on the agenda |
| Merging fails with a conflict message | A task on two teams' boards has no winning team | Decide the conflict, then merge again |
| Commit the PI plan greyed out | Blocking problems, unacknowledged warnings, or the Planning commit permission missing | Read the footer line and act on it |
| The drawer re-opened with a new review after commit | The plan changed after the review | Review the new changes and commit again |
| The session stayed in Review after committing | Some tasks were unticked | Merge and commit again to write them, or leave them planned |
| The PI goal in Planning lacks the ART objective | It is a Stretch objective; only committed ART objectives reach the goal | Switch it to Committed in step 2 |
| No calendar to pick | The project has no active Orbit Schedule calendar, or you cannot open its calendars | Create one in Orbit Schedule, or use Download (.ics) |
| Nothing new to create | Every event in the table is on the calendar already | Nothing; change an event's time or switch one on to create something new |
| A second set of events after changing the times | An event with a new start time is a new event | Delete the ones you do not want in Orbit Schedule |
| N of M events created (error) | Some events could not be created, for example you may not create events on that calendar | Check your rights in Orbit Schedule and press Create again: only the missing events are made |
| Load warnings in story points instead of hours | The session counts in story points, so the merge checks each team's load per iteration against its capacity | Compare with the team's capacity for that iteration, or tick Commit despite the warnings |
| Committing also needs the Planning — … permission | Your role lacks the Planning permission that commits scenarios to real tasks | Ask someone who holds it, or an administrator to grant it |