Risks and the ROAM session

What this page is — the Risks tab of a PI session and the ROAM session run from it: the train's risks, sorted into Resolved, Owned, Accepted and Mitigated, and the Day 2 agenda item where the room decides on each one.

What it is for — so every risk that could stop the train's plan is named, seen by everyone, and leaves the event with a decision: dealt with, owned by a person, accepted knowingly, or covered by a plan.

The problem it solves — risks raised on twenty sticky notes across three team boards are forgotten by Monday. Nobody knows which belong to the whole train, two teams raise the same vendor delay twice, and the confidence vote is taken without anyone saying who will act on the risk that matters most.

Route: /org/tasks/pi-planning?project=…&session=…&tab=risks · Permission to view: Open PI Planning sessions read-only: brief, team boards, program board, risks, discussion, objectives and review. · Permission to raise: Take part in a PI session as a team member: move cards on your own team's board, post, raise risks, propose cross-team dependencies, demo and vote.


1. Three levels of risk​

Team riskART-level team riskProgramme risk
Raised byA team member, on the team's boardA team member, then placed at ART levelThe RTE, or by combining team risks
Belongs toOne teamOne teamNo team — the whole train
Seen onThat team's board onlyThe team's board and the Risks tabThe Risks tab
ROAMed in the ROAM sessionNoYesYes
ExampleA tester on leave in Iteration 2Atlas: NPCI certification slot not yet confirmedFestive season code freeze starts 20 Nov — Iteration 3 is short

The Risks tab lists only ART-level and programme risks. A team's local risks stay on its board, in the Risks part of the board's side panel.

ROAM​

StateMeansRecorded with it
OpenRaised; nobody has taken it yet—
ResolvedAddressed — no longer a concernHow it was resolved (optional)
OwnedSomeone has taken responsibilityWho — required
AcceptedNothing more can be done; if it happens, the release may be compromisedWhat is accepted (optional)
MitigatedThe team has a plan to adjust as necessaryThe plan — required

2. Where it fits in the event​

MomentWhat happens
Day 1, Team breakoutsTeams raise risks on their boards at team level. The RTE can raise programme risks and place any team risk at ART level
Day 1, Management reviewA risk recorded there appears on the Risks tab at once
Day 2, Team breakouts (#2)Teams decide which of their risks are the train's and place them at ART level
Day 2, Final plan reviewSection 3 of each plan names the team's ART-level risks
Day 2, ART risks itemThe ROAM session: every ART-level and programme risk gets a ROAM state
Day 2, Confidence voteA voter's concern can be raised as a new risk

3. The Risks tab​

Figure 1 — The Risks tab on Day 1: one programme risk, still open.
#ElementWhat it does
1FilterFilter: all, programme level or one team's escalated risks
2Raise a riskRaise a risk. Opens a drawer on the right
3Combine hintTick risks that are really one programme risk to combine them. The tick boxes appear on the cards for the RTE only
4A risk cardA risk card in its ROAM column. It shows the title, the team or Programme, and the impact; hover or click it for the details, the owner and the edit and delete icons

The board is a strip of Open risks over a 2 × 2 of Resolved, Owned, Accepted and Mitigated. Drag a card to another cell to change its state; it moves at once and jumps back only if you are not allowed to change it.

Figure 2 — A risk opened for editing: its text, ROAM state, level, owner, impact and likelihood.

4. Step by step​

Raise a risk​

  1. On a team board, open the side panel's Risks part; on the session, open Risks and press Raise a risk.
  2. Type the Title and What could happen.
  3. Leave ROAM on Open unless the room has already decided.
  4. Choose Belongs to: your team, or Programme level (the RTE).
  5. For a team risk, choose Level: Team level (stays on the team's board) or ART level (on the session's Risks tab, for the whole train). From the Risks tab, ART level is pre-selected.
  6. Pick an Owner, an Impact and a Likelihood if known, and press Raise.

From a team board you can also link the stories the risk concerns, and the warning icon on a story card raises a risk already linked to it.

Place a team risk at ART level​

From Team breakout #2 on, anyone on the team whose role has the Risks right opens the risk and switches Level to ART level — or uses the up arrow in the side panel; the down arrow brings it back. Before Team breakout #2 the switch is greyed out: Team risks move to ART level in Team breakout #2 (Day 2). The RTE can do it at any time.

Combine team risks into one programme risk (RTE)​

  1. Tick two or more cards that describe the same thing.
  2. Press Combine N into a programme risk.
  3. Check the Programme risk title and the Description, which lists the originals; choose the ROAM state (Owned by default) and an Owner.
  4. Press Combine.

The originals show Part of a programme risk, the new one Combined, and the stories linked to the originals carry over.

Figure 3 — Combining two ticked risks into one programme risk.
#ElementWhat it does
1Programme riskThe new risk's title. It starts as the title of the first risk you ticked; reword it to name the shared cause
2DescriptionWhat it is about. It starts with the picked risks listed one per line, which are also shown above the fields
3ROAMThe new risk's ROAM state — Owned to start with
4OwnerWho owns it; searchable, Nobody yet allowed
5CombineCreates the programme risk. The ticked risks point at it and their linked tasks carry over. Greyed out while the title is empty

The tick boxes and Combine N into a programme risk appear for the RTE only, while the session is in planning, review or an adjustment round, and only on risks that are not already part of a programme risk.


5. The ROAM session​

Figure 4 — The Risks tab while the ROAM session is running.
#ElementWhat it does
1FilterFilter: all, programme level, or one team
2ROAM sessionROAM session — the RTE runs the risks one by one, on everyone's screen
3Raise a riskRaise a risk (team or programme level)
4The ROAM session is on:The session is on — everyone can join; the risk on screen is named. Join opens it full screen
5Combine hintTick team risks that are really one programme risk to combine them
6OpenOpen risks wait to be ROAMed
7ROAM cellsResolved, Owned, Accepted, Mitigated — the four ROAM outcomes
Figure 5 — The ROAM session: one risk on everyone's screen.
#ElementWhat it does
1N of M ROAMedHow many risks are ROAMed
2Collected risks & impedimentsThe collected risks, by team and programme; click one to put it on screen. A red mark is still open, a green one decided
3The risk on screenThe risk on everyone's screen, who raised it and who placed it at ART level, with its impact and likelihood
4TimerA timer for this risk: how long the room has spent on it
5The four choicesResolved, Owned, Accepted, Mitigated — one click places it (Owned asks for an owner, Mitigated for the plan)
6Within the team's control — back to the teamNot an ART risk after all — back to the team. After a confirmation it leaves the ART risks and stays on the team's board
7TalliesThe tally per ROAM state
8Arrows and End the sessionPrevious / next risk and End the session

Run it​

  1. Start the ART risks agenda item, open Risks and press ROAM session.
  2. The first open risk goes on everyone's screen. Read it out; let product management and the system architect help the room find the answer.
  3. Click one of the four choices and fill in what it asks for, then press, for example, Owned — next risk. The next open risk comes up by itself.
  4. Use Open it again to undo a decision on the risk on screen.
  5. When the left list is all green, press End the session.

Only management records decisions: the RTE, the Product Manager, the System Architect, the Business Owners and anyone with the run or manage permission. Everyone else reads The Release Train Engineer records what the room decides.

Figure 6 — Two risks decided; the next one is on screen.
#ElementWhat it does
1Owned cardOwned — Marco Rossi took responsibility, with a note
2Accepted cardAccepted — nothing more can be done; the plan allows for it
3Live lineThe next risk on screen — Phoenix's Apple Pay approval, placed at ART level

6. Field reference​

FieldControlRequiredValidationValues from
TitleTextYes1 to 200 charactersTyped
What could happenMulti-line textNo—Typed
ROAMFive buttonsYes (Open by default)—Open, Owned, Mitigated, Accepted, Resolved
Belongs toDrop-downYesA team in the sessionProgramme level and your own teams; the RTE sees every team. Shown on a new risk, and to the RTE when editing
LevelTwo-way switchFor team risksART level only from Team breakout #2, or by the RTETeam level, ART level
Linked storiesSearchable drop-downNoStories on the team's boardTeam boards only
OwnerSearchable drop-downNoA user of your organisationThe project's members
Impact, LikelihoodDrop-downsNo—Not set, Low, Medium, High
ROAM session: who takes responsibilitySearchable drop-downFor OwnedPre-filled with the risk's ownerThe project's members
ROAM session: the note or planMulti-line textFor MitigatedUp to 4,000 charactersTyped

Who may change what:

ActionWho
Raise a riskTeam members whose role has the Risks right, and the RTE, while the session is planning, in review or adjusting
Edit or drag a team's riskMembers of that team, and the RTE
Edit a programme risk, move a risk between teams, combineThe RTE
DeleteThe person who raised it, and the RTE
Send a risk back to its team in the ROAM sessionThe RTE

7. Why you would use it​

  • The train sees its real risks. Team-level noise stays on the boards; the Risks tab shows only what can hurt the whole train.
  • Duplicates become one decision. Combining three teams' "payments vendor is late" into one programme risk gives it one owner instead of three half-owners.
  • Every risk leaves with a decision. The ROAM session does not move on until the room says who acts, what is accepted, or what the plan is.
  • The vote is informed. Teams vote on confidence knowing which risks are owned and which accepted.

8. Worked example​

PI 2026.4 Planning, project Optima Orbit.

  1. Day 1. Maya Fernandes raises the programme risk Festive season code freeze starts 20 Nov — Iteration 3 is short, impact High. Lukas Novak raises NPCI certification slot not yet confirmed on the Atlas board at team level.
  2. Day 2, Team breakouts. Lukas switches the Atlas risk to ART level; it now appears on the Risks tab with From the team. Phoenix places Apple Pay merchant approval may take 3 weeks at ART level.
  3. Final plan review. Atlas's section 3 names the NPCI risk.
  4. ART risks, 13:00. Maya presses ROAM session. The NPCI risk goes on screen: Raised by Lukas Novak · placed at ART level by Lukas Novak. Marco Rossi, Atlas's product owner, will chase the certification. Maya clicks Owned, picks Marco Rossi, adds a note, and presses Owned — next risk.
  5. The code freeze comes up. Nothing can move it; the plan leaves Iteration 3 light. Maya clicks Accepted and presses Accepted — next risk.
  6. Phoenix's Apple Pay risk comes up. The team will submit early and fall back to card checkout: Maya clicks Mitigated, types that plan, and confirms.
  7. The counter reads 3 of 3 ROAMed. Maya presses End the session and closes the agenda item; the confidence vote follows.

9. Before this works — what an administrator sets up​

NeededWithout it
The Risks right for team roles in Roles & permissionsTeam members cannot raise or place risks
A Day 2 agenda item with breakout in its titleTeams can place risks at ART level only once the first planning or adjusting item of Day 2 starts
A switched-on ART risks item on the agendaNo timebox for the ROAM session; the button works regardless
Product Manager, System Architect and Business Owners named for the sessionOnly the RTE records the ROAM decisions; named, they can record them too
Run a PI session: start, pause and end the timer, breaks, broadcasts, category allocation, conflicts, risk synthesis, restart and merge. for the RTENobody can combine risks — except the named facilitator

10. Downstream effects​

WhereWhat it uses
Final plan reviewSection 3 lists the team's ART-level risks
Confidence voteRaise as a risk turns a voter's concern into a risk here
Plan reworkTeams rework knowing which risks are only accepted
Post-PI PlanningThe integrated ART risks travel with the committed plan

11. Don't confuse this with…​

ThisIs notBecause
A riskA dependencyA dependency is a story that waits for another team's story; see the ART Planning Board
AcceptedResolvedAccepted means the risk still exists and the train lives with it; resolved means it is gone
Accepted on one riskAccept the risks and move ahead in the confidence voteROAM decides one risk at a time; the vote's decision answers a low confidence score for a whole team or the train, and changes no risk's ROAM state
Within the team's control — back to the teamDeletingThe risk stays on the team's board, at team level
CombiningDeleting duplicatesThe originals stay, pointing at the programme risk

12. Troubleshooting​

SymptomCause and fix
A team risk is not on the Risks tabIt is at team level. Place it at ART level from Team breakout #2
Level is greyed outTeam breakout #2 has not started, or you are not on that team with the Risks right
No Raise a risk buttonThe session is not planning, in review or adjusting, or you are neither on a team nor the RTE
No tick boxes on the cardsOnly the RTE combines risks
Owned — next risk stays greyed outPick who takes responsibility
Mitigated — next risk stays greyed outType the plan
Clicking a risk in the ROAM session does nothingOnly management moves the session; you follow the risk on screen
A combined risk's originals are not in the ROAM sessionThey are part of the programme risk, which is ROAMed instead
No ROAM session buttonThere are no ART-level or programme risks yet
The header clock reads Review · the planning clock is stopped during the ART risks itemThe item runs while the session is in Review, and the planning clock runs only in the breakouts and adjustment rounds. It is not an overrun; Time is up shows only when the time is really used up

Where team risks are raisedTeam boards
Where risks are named per teamFinal plan review
What followsConfidence vote