What this page is — the Risks tab of a PI session and the ROAM session run from it: the
train's risks, sorted into Resolved, Owned, Accepted and Mitigated, and the Day 2 agenda item where the
room decides on each one.
What it is for — so every risk that could stop the train's plan is named, seen by everyone, and
leaves the event with a decision: dealt with, owned by a person, accepted knowingly, or covered by a
plan.
The problem it solves — risks raised on twenty sticky notes across three team boards are forgotten
by Monday. Nobody knows which belong to the whole train, two teams raise the same vendor delay twice,
and the confidence vote is taken without anyone saying who will act on the risk that matters most.
Route:/org/tasks/pi-planning?project=…&session=…&tab=risks · Permission to view: Open PI
Planning sessions read-only: brief, team boards, program board, risks, discussion, objectives and
review. · Permission to raise: Take part in a PI session as a team member: move cards on your own
team's board, post, raise risks, propose cross-team dependencies, demo and vote.
Figure 1 — The Risks tab on Day 1: one programme risk, still open.
#
Element
What it does
1
Filter
Filter: all, programme level or one team's escalated risks
2
Raise a risk
Raise a risk. Opens a drawer on the right
3
Combine hint
Tick risks that are really one programme risk to combine them. The tick boxes appear on the cards for the RTE only
4
A risk card
A risk card in its ROAM column. It shows the title, the team or Programme, and the impact; hover or click it for the details, the owner and the edit and delete icons
The board is a strip of Open risks over a 2 × 2 of Resolved, Owned, Accepted and
Mitigated. Drag a card to another cell to change its state; it moves at once and jumps back only if
you are not allowed to change it.
Figure 2 — A risk opened for editing: its text, ROAM state, level, owner, impact and likelihood.
On a team board, open the side panel's Risks part; on the session, open Risks and press
Raise a risk.
Type the Title and What could happen.
Leave ROAM on Open unless the room has already decided.
Choose Belongs to: your team, or Programme level (the RTE).
For a team risk, choose Level: Team level (stays on the team's board) or ART level (on
the session's Risks tab, for the whole train). From the Risks tab, ART level is pre-selected.
Pick an Owner, an Impact and a Likelihood if known, and press Raise.
From a team board you can also link the stories the risk concerns, and the warning icon on a story card
raises a risk already linked to it.
From Team breakout #2 on, anyone on the team whose role has the Risks right opens the risk and switches
Level to ART level — or uses the up arrow in the side panel; the down arrow brings it back.
Before Team breakout #2 the switch is greyed out: Team risks move to ART level in Team breakout #2
(Day 2). The RTE can do it at any time.
Tick two or more cards that describe the same thing.
Press Combine N into a programme risk.
Check the Programme risk title and the Description, which lists the originals; choose the
ROAM state (Owned by default) and an Owner.
Press Combine.
The originals show Part of a programme risk, the new one Combined, and the stories linked to the
originals carry over.
Figure 3 — Combining two ticked risks into one programme risk.
#
Element
What it does
1
Programme risk
The new risk's title. It starts as the title of the first risk you ticked; reword it to name the shared cause
2
Description
What it is about. It starts with the picked risks listed one per line, which are also shown above the fields
3
ROAM
The new risk's ROAM state — Owned to start with
4
Owner
Who owns it; searchable, Nobody yet allowed
5
Combine
Creates the programme risk. The ticked risks point at it and their linked tasks carry over. Greyed out while the title is empty
The tick boxes and Combine N into a programme risk appear for the RTE only, while the session is in
planning, review or an adjustment round, and only on risks that are not already part of a programme risk.
Start the ART risks agenda item, open Risks and press ROAM session.
The first open risk goes on everyone's screen. Read it out; let product management and the system
architect help the room find the answer.
Click one of the four choices and fill in what it asks for, then press, for example, Owned — next
risk. The next open risk comes up by itself.
Use Open it again to undo a decision on the risk on screen.
When the left list is all green, press End the session.
Only management records decisions: the RTE, the Product Manager, the System Architect, the Business
Owners and anyone with the run or manage permission. Everyone else reads The Release Train Engineer
records what the room decides.
Figure 6 — Two risks decided; the next one is on screen.
#
Element
What it does
1
Owned card
Owned — Marco Rossi took responsibility, with a note
2
Accepted card
Accepted — nothing more can be done; the plan allows for it
3
Live line
The next risk on screen — Phoenix's Apple Pay approval, placed at ART level
The train sees its real risks. Team-level noise stays on the boards; the Risks tab shows only what
can hurt the whole train.
Duplicates become one decision. Combining three teams' "payments vendor is late" into one
programme risk gives it one owner instead of three half-owners.
Every risk leaves with a decision. The ROAM session does not move on until the room says who acts,
what is accepted, or what the plan is.
The vote is informed. Teams vote on confidence knowing which risks are owned and which accepted.
Day 1. Maya Fernandes raises the programme risk Festive season code freeze starts 20 Nov —
Iteration 3 is short, impact High. Lukas Novak raises NPCI certification slot not yet confirmed
on the Atlas board at team level.
Day 2, Team breakouts. Lukas switches the Atlas risk to ART level; it now appears on the Risks
tab with From the team. Phoenix places Apple Pay merchant approval may take 3 weeks at ART level.
Final plan review. Atlas's section 3 names the NPCI risk.
ART risks, 13:00. Maya presses ROAM session. The NPCI risk goes on screen: Raised by Lukas
Novak · placed at ART level by Lukas Novak. Marco Rossi, Atlas's product owner, will chase the
certification. Maya clicks Owned, picks Marco Rossi, adds a note, and presses Owned — next
risk.
The code freeze comes up. Nothing can move it; the plan leaves Iteration 3 light. Maya clicks
Accepted and presses Accepted — next risk.
Phoenix's Apple Pay risk comes up. The team will submit early and fall back to card checkout: Maya
clicks Mitigated, types that plan, and confirms.
The counter reads 3 of 3 ROAMed. Maya presses End the session and closes the agenda item; the
confidence vote follows.
9. Before this works — what an administrator sets up
It is at team level. Place it at ART level from Team breakout #2
Level is greyed out
Team breakout #2 has not started, or you are not on that team with the Risks right
No Raise a risk button
The session is not planning, in review or adjusting, or you are neither on a team nor the RTE
No tick boxes on the cards
Only the RTE combines risks
Owned — next risk stays greyed out
Pick who takes responsibility
Mitigated — next risk stays greyed out
Type the plan
Clicking a risk in the ROAM session does nothing
Only management moves the session; you follow the risk on screen
A combined risk's originals are not in the ROAM session
They are part of the programme risk, which is ROAMed instead
No ROAM session button
There are no ART-level or programme risks yet
The header clock reads Review · the planning clock is stopped during the ART risks item
The item runs while the session is in Review, and the planning clock runs only in the breakouts and adjustment rounds. It is not an overrun; Time is up shows only when the time is really used up