PI objectives and business value

What this page is — the Objectives tab of a PI session: the train's own objective, every team's committed and stretch objectives, the business value the Business Owners give each one, and, after the PI, the value each actually delivered.

What it is for — so each team says in business terms what its plan achieves, and the Business Owners say how much each result is worth, before anyone votes on the plan.

The problem it solves — a board full of stories says what will be built, not why it matters. Without objectives and business value the final plan review has nothing to accept, the Business Owners cannot compare teams, and after the PI there is no way to measure whether the train delivered what it promised.

Route: /org/tasks/pi-planning?project=…&session=…&tab=objectives · Permission to view: Open PI Planning sessions read-only: brief, team boards, program board, risks, discussion, objectives and review. · Permission to write objectives: Take part in a PI session as a team member: move cards on your own team's board, post, raise risks, propose cross-team dependencies, demo and vote.


1. Objectives, stretch objectives and the ART objective​

Project (ART) objectiveCommitted team objectiveStretch objective
SaysWhat the whole train commits toA result one team commits to deliverA result the team plans for but does not promise
Written byThe RTE, or anyone with the manage permissionThe teamThe team
Business valueNonePlanned business value (PBV) 1–10 by a Business OwnerPBV 1–10 as well
Counts in the team's BV total—YesNo
Becomes, at mergeThe PI's goalOne of the goal's success criteriaNothing
Actual value (ABV) after the PI—Scored 0–10Not scored

Business value is the Business Owners' judgement of how much a result matters to the business, on a scale of 1 to 10. It is not effort and not story points: a two-point story can carry the objective with the highest value.


2. Where it fits in the event​

MomentWhat happens to objectives
Day 1, Team breakoutsTeams write objectives on their board's side panel or on this tab. PBV stays empty
Day 1, Draft plan reviewEach team presents its draft objectives. The plan is saved as the Day 1 plan when the review closes
Day 2, Team breakouts (#2)Teams adjust objectives to the management adjustments; the Business Owners walk the room and score PBV
Day 2, Final plan reviewEach team's final objectives with PBV, and what changed since Day 1
Post-PI Planning, mergeThe ART objective becomes the PI's goal; each committed objective one of its success criteria
Post-PI Planning, after the commitThe RTE can still write or change ART objectives there (step 2); each change reaches the PI's goal at once
After the PIThe RTE scores each committed objective's actual value; the tab shows predictability

3. The screen on Day 1​

Figure 1 — Day 1: objectives written, business value not scored yet.
#ElementWhat it does
1Project objectiveThe project (ART) objective — what the whole train commits to; it becomes the PI's goal. The plus button adds it
2A team cardEach team's objectives, committed first. The plus button adds one, the pencil edits it, the bin deletes it after a confirmation
3StretchStretch = uncommitted. It is planned work the team does not promise
4PBVPlanned business value — empty until the business owners score it in Team breakout #2. Hovering the label explains why the slider is greyed out

A title is edited where it stands: click it, type, press Enter or click away to save, Esc to cancel.


4. The screen on Day 2​

Figure 2 — Day 2: a Business Owner scores business value.
#ElementWhat it does
1The ART objectiveThe ART's objective — the PI's goal for the whole train
2A team objectiveA team objective, its title and its slider
3PBVPBV — the business owner drags it 1–10 (from Team breakout #2). The number at the end shows the value; the small cross clears it
4StretchStretch objectives carry business value too, but are not committed, so they do not count in the team's BV total

The BV chip on each team card is the sum of its committed objectives' PBV: Phoenix 10 + 7 = 17; the stretch objective's 3 is left out.

A Business Owner who is in no team

Sofia Alvarez belongs to no team, so the session tells her what her role lets her do instead: You take part as a Business Owner, not in a team: you set the business value of the teams' PI objectives (from Team breakout #2), … and vote in the ART confidence vote. Planning the team boards is for their teams. The middle of the list follows the project's rule book. Scoring business value is her role, not a team member's. Only someone with no team and no ART role reads You are following this session as an observer: everything is visible, nothing can be changed.


5. Step by step​

Write a team objective​

  1. Open Objectives and press the plus on your team's card — or use the Objectives part of your board's side panel.
  2. Type the Objective, add Details if the title needs a sentence of context.
  3. Switch on Stretch objective if the team plans the work but does not promise it.
  4. Press Add.
Figure 3 — Adding a team objective for Phoenix.
#ElementWhat it does
1New objective — "team"A result the team commits to in this PI. Opened from the plus on the team's card. The plus on Project objective opens the same drawer for the ART objective, without marks 4 and 5
2ObjectiveThe objective, in one line — up to 300 characters. Add stays greyed out until it is filled
3DetailsMore detail, if the line needs a sentence of context
4Planned business value (1–10)Set by the Business Owners (or the RTE) from the Day 2 Team breakouts on. Before that, or for anyone else, the slider is greyed and a line under it says why
5Stretch objectivePlanned but not committed: it does not count in the committed business value, the PI goal or the predictability figure
6AddAdds it to the team's card. Cancel closes the drawer

On the board's side panel the objectives sit in Committed and Uncommitted sections; drag one between them to change it.

Write the ART objective (RTE)​

Press the plus on Project objective, type what the whole train commits to, and press Add. The drawer says It becomes the PI phase's goal when the plans are merged. After the commit no objective is written on this tab any more (only actual value is scored); ART objectives are then written in Post-PI Planning step 2, and still reach the PI's goal.

Score business value (Business Owner or RTE)​

  1. Wait for the Day 2 Team breakouts item to start. Before that the slider is greyed out with the hint Business owners set the business value in Team breakout #2 (Day 2).
  2. Talk the objective through with the team.
  3. Drag the PBV slider, or focus it and use the arrow keys. It saves a moment after you stop.
  4. Press the cross to clear a value scored by mistake.

Score actual value after the PI (RTE)​

Once the session is committed, each committed objective shows a number field with the tooltip Actual value delivered (0–10), after the PI. Type the value and leave the field. A Delivered chip appears, and the top of the tab shows N% predictability — actual value delivered against the business value the teams committed to.


6. Field reference​

FieldControlRequiredValidationWho may set it
ObjectiveText field, or in-place edit of the titleYes1 to 300 charactersTeam members whose role has the Objectives right on that team; the RTE for any team. The project objective: the RTE or the manage permission
DetailsMulti-line textNo—As above
Planned business value (1–10)10-stop slider with a clear buttonNoWhole numbers 1 to 10Business Owners and the RTE, from the Day 2 Team breakouts item on
Stretch objectiveSwitchNo (off = committed)—As for the title
Actual valueNumber fieldNo0 to 10, set on its ownThe RTE or the manage permission, once the session is committed or closed

Objectives can be written and edited while the session is in Briefing, Planning, Review or Adjusting. Who counts as a team member and which roles hold the Objectives right come from the project's Roles & permissions rule book.

When Team breakout #2 starts: the first switched-on agenda item on Day 2 or later whose title contains breakout. In a session without an agenda, business value opens when an adjustment round starts.


7. Why you would use it​

  • The plan gets a purpose. "Shoppers pay with a saved card in one tap" is something a Business Owner can value; eleven story points are not.
  • Priorities become visible. PBV lets the Business Owners rank results across teams before the vote, so trade-offs on Day 2 are made on value.
  • Stretch keeps promises honest. Work the team may not finish stays visible without inflating what the train commits to.
  • Predictability is measurable. Actual against planned value, after the PI, is the train's predictability figure — the measure SAFe uses to judge whether planning works.

8. Worked example​

PI PI 2026.4 in project Optima Orbit.

  1. Day 1, Team breakouts. Phoenix writes Shoppers pay with a saved card in one tap and Wallet payments on iOS and Android, and the stretch objective Browse the catalogue offline. Atlas writes two committed objectives and the stretch Self-serve mandate management; Orion writes two.
  2. Day 1, Draft plan review. The objectives are presented without business value; the review closes and the Day 1 plan is saved.
  3. Day 2, Team breakouts. Maya Fernandes writes the project objective Shoppers pay in one tap on any network — card or UPI — for the investor demo. Sofia Alvarez opens Objectives and scores Phoenix 10, 7 and 3, Atlas 9, 8 and 4, Orion 6 and 5. The team cards show BV 17, BV 17 and BV 11.
  4. Final plan review. Phoenix's section 2 shows Shoppers pay with a saved card in one tap: BV — → 10 and 2 committed · planned business value 17 · 1 stretch.
  5. Post-PI Planning. The merge makes the project objective the PI's goal, with each committed team objective as a success criterion.
  6. After the PI. Maya scores actual value: 10 and 5 for Phoenix, 9 and 8 for Atlas, 6 and 5 for Orion. The tab shows 43 of 45 committed points delivered: 96% predictability.

9. Before this works — what an administrator sets up​

NeededWithout it
Business Owners named for the sessionOnly the RTE can score business value
A Day 2 agenda item with breakout in its titleBusiness value opens with the first planning or adjusting item on Day 2 that is not Planning adjustments
The Objectives right for team roles in Roles & permissionsTeam members see the tab read-only
Run a PI session: start, pause and end the timer, breaks, broadcasts, category allocation, conflicts, risk synthesis, restart and merge. or Create, edit and close PI sessions, choose the participating teams, and edit the project's PI Planning settings.Nobody can write the project objective or score actual value — except the named facilitator

10. Downstream effects​

WhereWhat it uses
Final plan reviewSection 2: final objectives, PBV and changes since Day 1; the committed count and planned value in Accepted so far
Confidence voteTeams vote on a plan whose objectives and value are known
Post-PI PlanningThe PI goal and its success criteria, written as team name, objective and value
Board side panelThe same objectives, edited in place

11. Don't confuse this with…​

ThisIs notBecause
Planned business valueStory points or capacityIt measures worth to the business, set by Business Owners, not effort
A stretch objectiveA postponed featureStretch work is still in the plan; a postponed feature has left the iterations. See Planning adjustments
The project objectiveAn iteration goal on the team boardIteration goals describe one team's iteration; the project objective the whole PI
Actual valuePlanned value edited laterActual value is a separate score, kept beside the planned one

12. Troubleshooting​

SymptomCause and fix
The PBV slider is greyed outDay 2 Team breakouts has not started, or you are not a Business Owner or the RTE. Hover PBV for the reason
A Business Owner sees You take part as a Business Owner, not in a teamThey belong to no team. The note lists what the role allows; business value is scored here from Team breakout #2
Someone sees You are following this session as an observerThey have no team and no ART role in the session. Name them as an ART role, or add them to a team
No plus button on the Project objectiveOnly the RTE and the manage permission write it
A team's BV total looks too lowStretch objectives are left out of the total
No plus button on your team's cardYour role has no Objectives right in the rule book, or the session is committed
The predictability line does not appearNo committed objective with planned value has an actual value yet
The actual value field is missingThe session is not committed yet, or the objective is a stretch objective

Where teams re-plan on Day 2Team boards
Where the final objectives are presentedFinal plan review
Where they become the PI goalPost-PI Planning