ART Planning Board
What this page is — a guide to the ART Planning Board tab of a PI Planning session: the whole release train's plan on one screen, in four views — ART board, Load, Dependencies and Links — plus Propose a dependency and a full-screen mode for the big room.
What it is for — seeing, at a glance, when each feature lands, which team waits on which, which milestones the features serve, and where the plan is weak, so the RTE and the teams fix it while they are still planning.
The problem it solves — each team board looks fine on its own. The train's plan fails at the seams: a feature that cannot finish because the work it waits for lands an iteration later, a team that has no dependencies because it has not understood its work yet, a demo milestone that no feature is lined up for. Those only show when every team is on one board.
Route: Orbit Ops → PI Planning → open a session → ART Planning Board under The whole train (ART)
(/org/tasks/pi-planning?project=…&session=…&tab=program)
· Permission to view: Open PI Planning sessions read-only: brief, team boards, program board, risks, discussion, objectives and review.
· Permission to propose a dependency: Take part in a PI session as a team member: move cards on your own team's board, post, raise risks, propose cross-team dependencies, demo and vote.
1. Features, not stories
This is SAFe's program board. Where a team board shows stories, this board shows features: each team plans its stories, and the board works out from them where each feature finishes. It fills in as soon as the session is published and the teams start planning; before that it reads Nothing to show yet.
| ART Planning Board | Team board | Risks tab | |
|---|---|---|---|
| Rows | One lane per team, milestones on top | One team | — |
| What sits in the cells | Features, significant dependencies, milestones | Stories and tasks | ART and programme risks |
| Who moves things | A team moves its own feature's target; the RTE any | The team, within its roles | Whoever owns the risk |
| What it tells you | When each feature lands and what it waits for | What each person does in each iteration | What could stop the train |
The colours of the board are fixed: blue is a feature, red is a significant dependency, the orange diamond is a milestone or event, and a red string ties a dependency to the feature that waits for it.
2. Why you would use it
- Catch late dependencies while they are cheap to fix. A string that lands after the feature it serves, or after the iteration it is needed by, is drawn dashed and counted at the top.
- Spot teams that have not understood their work. A delivery team with no dependency at all is counted under What to look out for — usually a sign the work has not been broken down far enough.
- Line features up with events. Each milestone is strung to the features whose stories contribute to it, and a feature planned after its milestone is flagged.
- Run the dependency sync. In the room, full screen, the RTE walks the strings team by team; teams answer the open dependencies in Links.
- Check load across the train. The Load view puts every team's iterations side by side.
3. Where it fits in the event
| When | What the board is used for |
|---|---|
| Team breakout #1 (Day 1) | The RTE watches it fill and calls the dependency sync; teams propose and answer dependencies |
| Draft plan review and management review | The picture of the train management reads; the cross-team dependencies feed the management review |
| Team breakout #2 (Day 2) | Teams re-plan after management's decisions; strings that were dashed should turn solid |
| Final plan review and after | The record of when each feature lands and what the train agreed to depend on |
Feature targets can be moved while the teams plan (planning or an adjustment round); the RTE can move them at any time before the plan is committed. Dependencies can be proposed and answered while the session is planning, in review or adjusting.
4. The ART board view
| # | Element | What it does |
|---|---|---|
| 1 | View switcher | ART board, Load, Dependencies and Links — the number on Links is the count of cross-team dependencies. The team names beside it are the colour key |
| 2 | What to look out for | Five counters, green at zero and amber otherwise; hover one for what it means and which teams it names |
| 3 | Legend | Feature, significant dependency, milestone / event, string, dashed (out of order), and the pin for a target set by the team |
| 4 | Milestone or event | An orange diamond in the iteration its date falls in, strung (dotted, orange) to the features whose stories contribute to it |
| 5 | Feature card | A feature in the iteration its team expects to finish it, with stories planned / stories in total. Hover it for the iterations its stories span |
| 6 | Significant dependency | A red card in the lane of the team that provides the work, in the iteration that work is planned in. The label is the story key and → the feature that waits, with · waiting until it is accepted |
| 7 | Propose a dependency | Opens the proposal drawer. Shown to team members and the RTE while dependencies can be proposed |
| 8 | Full screen | The board alone, for the screen in the big room. Exit full screen returns |
Where a feature sits
A feature sits in the iteration where its last planned story ends. A team can override that: drag the feature to another iteration, or to Next PI >>>, to set a delivery target. A pinned feature shows the pin icon; dragging it to Not planned clears the target. You can only drag your own team's features, and only if your role has the Plan right on your board; the RTE can drag any.
The Not planned column appears only when a feature has no planned story and no target. Next PI >>> is always the last column. System teams (shared services named on the session) get their own lanes below a thick line.
What to look out for
| Counter | It counts | Why it matters |
|---|---|---|
| teams with no dependencies | Delivery teams with no proposed or accepted dependency | Usually the work is not understood well enough yet |
| out of order | Dependencies that land after the feature that waits, or after the iteration they are needed by, or are not planned — drawn as dashed strings | The feature cannot finish on time |
| after their milestone | Features expected done after the milestone they contribute to | The event will not have the feature |
| targets before their stories | Features a team pinned earlier than the last story planned for them | The target is wishful |
| not planned | Features with no story in the iterations and no target | Nobody has planned it yet |
Only dependencies that have been pushed — waiting for an answer, or accepted — are drawn. Drafts and declined dependencies stay off the board. Hover a card to thicken its strings.
5. The other views
Load
Teams down the side, iterations across. Each cell shows the number of tasks (1 task, 3 tasks), the hours planned, a bar, and the capacity of the team's people in that iteration. The bar turns red when the work is above the project's overload ratio (from Planning settings, 110 % unless changed). The All teams row adds them up and joins the teams' iteration goals.
This view always counts estimated hours against the people's available hours, whatever the session's measure. In a story-point session, use the capacity cards on each team board, or the draft plan review, to judge load in points.
When someone belongs to two teams, a Shared people card appears above the views: their capacity counts once and their load is the sum of every team's work.
Dependencies
The story-level picture: teams as rows, the backlog and iterations as columns, and a line from the work that is waited for to the story that waits. A red line and a red-outlined tile mean the order is wrong — the work it waits for does not end before the waiting story can start, or is not planned. Hover the tile for the reason; a fix button suggests the smallest move that would put it right.
While the teams plan, you can drag a tile to another iteration: the move is made on the owning team's board. You can move only your own team's tiles (Not your team's task — ask Atlas to move it, or propose a dependency); the RTE can move any. Links on a whole feature are not drawn here; they are listed in Links.
Links
Every pushed cross-team dependency as a table: Needs (the team and story that waits, with its note), From (the team and story or feature it waits for), Needed by, and Status with who proposed it.
| Action | Who may do it |
|---|---|
| ✓ Accept — your team will deliver it in time | The lead or scrum master of the team in From, or the RTE |
| ✗ Decline — your team cannot commit to it | The same |
| Remove the link | The person who proposed it, or the RTE |
Only accepted links become real task dependencies when the plan is committed.
6. Propose a dependency, step by step
- Press Propose a dependency.
- This task (waits) — the task that needs the other team's work. The list holds every team's tasks, grouped by team.
- Needs this task (from another team) — the work it waits for.
- Kind — finish to start (the default), start to start, finish to finish or start to finish.
- Lag (days) and Needed by, if they matter, and a Note.
- The footer reads, for example, Phoenix waits for Atlas. Press Propose.
| # | Element | What it does |
|---|---|---|
| 1 | This task (waits) | The task that needs the other team's work first |
| 2 | Needs this task (from another team) | The other team's task it waits for. Picking two tasks of the same team is refused |
| 3 | Kind | Finish to start, start to start, finish to finish or start to finish — each option says what it means |
| 4 | Lag (days) | Days between the two; a negative number lets them overlap |
| 5 | Needed by | When it is needed — an iteration of the PI, or No date — just the order |
| 6 | Note | Why it is needed, or what exactly |
| 7 | Propose | Sends it — the other team's lead or scrum master accepts or declines it. Greyed out until both tasks are picked; the footer says what is missing (Pick both tasks., Pick two different tasks.) or, once valid, which team waits for which |
Field reference
| Field | Control | Required | Validation | Where the values come from |
|---|---|---|---|---|
| This task (waits) | Searchable picker | Yes | Must differ from the other task | Every task on the session's team boards |
| Needs this task | Searchable picker | Yes | Must be on another team's board — Both tasks are on the same team's board — link them on that board's Dependencies view instead | The same list |
| Kind | Picker | Yes, defaults to finish to start | — | Fixed list of four |
| Lag (days) | Number | No, 0 | −365 to 365 | Typed |
| Needed by | Picker | No — No date — just the order | — | The PI's iterations |
| Note | Text | No | Up to 500 characters | Typed |
A dependency proposed here is sent at once: it is Waiting for an answer, and it shows on both teams' boards. The other team's lead and scrum master get a bell, Dependency to answer: PI 2026.4 Planning, reading Phoenix needs work from your team — accept or decline it on the ART Planning Board.; it opens this board. You must belong to one of the two teams, or be the RTE. On a team board, by contrast, a new dependency starts as a draft until the team pushes it — see Team boards.
7. Worked example: the dependency sync on Day 1
Midway through Team breakouts, Maya Fernandes (RTE) opens the ART Planning Board and presses Full screen.
- Phoenix's lane holds Mobile Checkout 2.0 (5/5 stories planned) and Offline mode (2/3) in Iteration 3; Atlas's holds Fraud scoring v2 and UPI AutoPay mandates; Orion's holds Observability platform, an enabler.
- Two red cards sit in Iteration 1: Atlas's OO-CORE-22750 → Mobile Checkout 2.0 · waiting and Orion's OO-CORE-22753 → Mobile Checkout 2.0 · waiting. Both strings run solid to Mobile Checkout 2.0: the work lands before the feature finishes and before Iteration 2, when Phoenix needs the fingerprints.
- What to look out for is all green: every team has dependencies, nothing is out of order.
- Maya notices that Investor Demo (10 Nov) has no string. On the Milestone view of Phoenix's board, Arjun Rao drags Mobile Checkout 2.0 onto Investor Demo; back on the ART board an orange dotted string now joins them.
- Maya switches to Links. Both rows read Waiting for an answer. Lukas Novak, Atlas's lead, presses ✓ on the fingerprints row from his own screen; Olivia Brown does the same for tracing. Both turn Accepted.
- On Load, Atlas carries the most hours in Iteration 1 (108 h), which Maya notes for the management review.
8. The admin contract
| Must be in place | Where | What happens without it |
|---|---|---|
| A published session with teams | The session setup (Create a session) | Nothing to show yet |
| Features given to teams | Features & teams (Features and teams) | No feature is given to a team yet and empty lanes |
| Leads and scrum masters named in each team | Organization Settings → Planning Teams (Planning teams) | Nobody but the RTE can accept or decline that team's dependencies, and nobody is notified |
| Milestones with dates in the PI | The project's Roadmap | The Milestones / events row stays empty |
| System teams, if you have them | The session's roles | Shared-service teams are drawn as ordinary delivery lanes and counted under teams with no dependencies |
| The overload ratio | Project settings → Planning (Project planning settings) | Load turns red above 110 % |
9. Downstream effects
- Accepted links become task dependencies at merge & commit; declined ones are dropped.
- Open and declined dependencies are counted in the management review's Cross-team dependencies card.
- A team's feature targets stay with the session and are shown again on Day 2.
- A tile dragged in the Dependencies view moves the story on its team's board, as if the team had moved it.
10. Don't confuse this with…
- Team boards — one team's stories and its own dependency drafts. See Team boards.
- Plan by Dependencies on a team board — a quick form and one team's lists; the ART board shows every team.
- The Risks tab — ART-level risks, not dependencies. See Risks and ROAM.
- Scrum of Scrums — the teams' answers to checkpoint questions, including whether they have begun resolving dependencies. See Scrum of Scrums.
11. Troubleshooting
| What you see | Why | What to do |
|---|---|---|
| Propose a dependency is missing | You are in no team and not the RTE, or the session is committed | Ask a team member to propose it |
| A dependency is on the team board but not on the ART board | It is still a draft, or it was declined | Push it from the team board |
| A string is dashed | The work lands after the feature, after its needed-by iteration, or is not planned | Bring the work forward on the providing team's board, or move the waiting story |
| You cannot drag a feature | It is another team's feature, your role lacks the Plan right, or the teams are not planning | Ask that team, or the RTE |
| ✓ and ✗ are missing on a row | Only the providing team's lead or scrum master, or the RTE, answers | Ask them |
| A bell … needs work from your team — accept or decline it on the ART Planning Board. | Another team pushed or proposed a dependency on your team's work | Open the bell; answer it in Links or on your team panel's Dependencies tab |
| Not your team's task when dragging a tile | The tile belongs to another team | Ask that team to move it |
| Load shows hours in a story-point session | Load always counts hours from people's capacity | Read points on the team boards' capacity cards |
| A milestone has no string | No story of any feature contributes to it | Use Plan by Milestone on the team board |