Features & teams

What this page is — the Features & teams tab of a PI session, headed Who plans what: the board where each feature in the PI is given to the team that will plan it, together with tasks that have no feature, single tasks handed to a different team, and the conflicts that remain.

What it is for — deciding, in the room and in front of everyone, which team's board each piece of work lands on, so that every team starts its breakout with exactly its own features and nothing else.

The problem it solves — if nobody decides who plans a feature, its stories land on no board and are silently left out of the PI; if two teams think they own it, the same story is planned twice and the merge has to untangle it. This tab makes both cases visible before the breakouts start.

Route: /org/tasks/pi-planning?project=…&session=…&tab=allocation · Permission: Open PI Planning sessions read-only: brief, team boards, program board, risks, discussion, objectives and review. (to see it) · Run a PI session: start, pause and end the timer, breaks, broadcasts, category allocation, conflicts, risk synthesis, restart and merge. (to place features for any team) · Take part in a PI session as a team member: move cards on your own team's board, post, raise risks, propose cross-team dependencies, demo and vote. (for a product owner picking their own team's features)


1. It opens with the product vision​

In a session that runs an agenda, features are given to teams once the "Product / solution vision" agenda item has started — the moment the Product Manager has explained what the PI is for. Before that the tab is visible but nothing can be dragged, and its introduction ends with Teams take their features when "Product / solution vision" starts on the agenda.

Before the vision item startsFrom the vision item on, during the briefingDuring Team breakoutsIn an adjustment round
RTE places any feature, changes the PI's scope, tasks without a feature, single tasksNoYesOnly taking and releasing featuresYes
A product owner (and the people they name) takes free features for their own team, releases their ownNoYesYesYes
Capacity measure can changeYes (RTE, managers)YesNo — fixedNo

If the vision item is switched off, the first switched-on item after it opens the tab; an agenda with no vision item at all opens it with its first planning item. A session without an agenda can be allocated from the draft on, and asks Publish with unallocated features? if any feature in the PI still has no team when you publish.


2. The screen before features are placed​

Figure 1 — Features & teams in a draft session: five features in the PI, no team holds any yet.
#ElementWhat it does
1Capacity inThe capacity measure: Hours, Days, Story points or Value (money). The RTE and managers change it in the draft and the briefing; it is fixed once planning starts and then shows as plain text
2Features with no team · NThe features in the PI's scope that no team holds yet, with a search box. Drop a team's feature back here to take it away
3A feature cardIts colour, its name, its open size in the session's measure and its number of open tasks. Hover the numbers for the split between the iterations and the backlog. An amber ⚠ with a number counts tasks not estimated. Drag it onto a team
4Not in this PI · NThe project's other features, folded. Unfold it to drag one into the PI, or drop a feature here to leave it out
5A team columnThe team's colour and name, Your team on your own, System team where it applies, and a members button. An amber triangle on that button says how many members cannot yet use their board; click it to see each person's role, share of time, skills and what to fix
6Picks featuresWho may give this team its features: its product owner, plus anyone they name. the facilitator when the team has no product owner
7Choose whoNames other members who may pick the team's features. Shown to the team's product owner, the RTE and managers
8Tasks without a feature, and single tasksWhere tasks with no feature go, and single tasks given to a team other than their feature's
9ConflictsWhat still needs a decision: planned work with no team, tasks on two boards, people in two teams

3. The screen once features are placed​

Figure 2 — The same tab after the vision item started and every feature was given a team.
#ElementWhat it does
1Phoenix's featuresPhoenix holds Mobile Checkout 2.0 and Offline mode — their open stories go to its board. The × on a card takes the feature away again
2Atlas's featuresAtlas holds UPI AutoPay mandates and Fraud scoring v2
3Orion's featureOrion, the platform team, holds the Observability enabler
4ConflictsNone — every task has one team and nobody is shared. Every feature in scope has a team

Under its features each team shows Capacity and Open tasks by type: a ring with the number of open tasks and their total size, split by task type.


4. Step by step​

Give a feature to a team​

  1. Wait for the RTE to start Product / solution vision. Features & teams gets a pulsing green dot in the rail.
  2. Open Features & teams. Your own team comes first.
  3. Drag a card from Features with no team onto the team. It shows there at once and is saved behind it; if it is refused, it goes back and a message says why.

While you drag, teams you may not give features to fade and show a lock.

Take a feature away, or move it​

Press the × on the card, or drag it back to Features with no team. Only the RTE — and roles that pick for every team, by default the Product Manager and the System Architect — can drag a feature straight from one team to another; a product owner releases their own team's feature and the other product owner takes it. After publishing, a feature that changes team takes its tasks to the new team's board, keeping the iteration or backlog place they were planned in.

Name who else picks a team's features​

Under each team, Picks features: names who may place features on it — the product owner, then anyone else named. Press Choose who beside it (shown to the team's product owner, the RTE and managers). A drawer titled "team" — who picks features opens.

Figure 3 — Choosing who, besides the product owner, picks Phoenix's features.
#ElementWhat it does
1Title and hintThe product owner picks the team's features; this drawer adds helpers
2The product ownerAlways ticked and greyed — a product owner cannot be taken off the list
3A memberTick to let this member pick features for the team too. Only the team's members in this session are listed
4SaveSaves the list; the team's Picks features: line updates. Cancel leaves it as it was

A helper can drag features onto and off their own team, exactly like the product owner. They cannot drag a feature straight from one team to another; that stays with the RTE and the roles that pick for every team.

See who is in a team​

The small people button beside a team's name (for example 5 for Phoenix) opens "team" — members. Its tooltip reads Members, skills and capacity; when it is amber with a triangle, it says how many members cannot use the board yet.

Figure 4 — A team's members, with their role, skills and share of time.
#ElementWhat it does
1The drawerEveryone in the team for this session
2TotalsMembers and full-time equivalents for this PI — the shares added up, so two 50 % people count as one
3Role and skillsThe person's role in the team (Product owner, Lead, Scrum master), and under the name their skills with level; the primary skill is the dark chip. No skills recorded means none are on their profile
4Share of timeThe share of their time in this team, from Planning Teams

When something stops a member from using their board, their card lists it in an amber box — for example a missing permission or not being a member of the project — and Joins from "team" for this PI shows when the person was moved in for this session only. Fix the cause in Planning Teams or the project's members, then reopen the drawer.

Decide where tasks without a feature go​

Pick a value in Tasks with no feature (N open) go to: Not in this PI, In this PI — no team yet, or a team. Press Save, or Discard.

Give a single task to another team​

Type at least two characters in Find a task to give to a team…, pick the team in the dropdown beside it, click the task (give to Phoenix), and press Save. The bin beside an override removes it and the task follows its feature again.

Decide a task that is on two boards​

Under Conflicts, each such task has a dropdown of the teams that hold it. The RTE picks the team that keeps it; by default the feature's team does. The merge at the end needs every one decided.

When tasks are outside the PI​

A team's board holds the open tasks of its features that are in this PI's sprints or in the backlog. A task in another phase or sprint cannot reach a board, so a team can hold features and still have nothing to plan. A warning above the board says how many tasks this affects and where they are, and an amber number on a feature shows its share.

  1. Click See why and what to do, or the amber number on a feature. A drawer lists the tasks by the milestone that holds them; click a task to open it in a new tab.
  2. Choose a way out: move the tasks into this PI's sprints or the backlog, add sprints where the work is, or start a session on the right PI. The PI of a published session cannot change.
  3. If you moved tasks into the PI, come back to this tab. A second notice counts them; the RTE clicks Bring onto the boards while the allocation is open. Nothing leaves a board, and a task a team dropped stays dropped.

People in more than one team​

When someone belongs to two teams, Conflicts lists them under N people are in more than one team (1 person is … for one), with the teams they are in, and the note Allowed — a shared specialist. Their load from every team counts against one capacity on the ART Planning Board. Nothing needs deciding; the line is there so the teams plan that person's time together.


5. Field and control reference​

ControlTypeRequiredValidationWhere the values come from
Capacity inDropdownYesDraft and briefing onlyFixed list: Hours, Days, Story points, Value (money)
Feature cardDrag and drop—A product owner may only take a free feature of the PI or release their own team's; another team already plans that feature — ask the facilitator to move itThe project's features
Find a feature…SearchNoMatches the name—
Choose whoCheckboxes in a drawerNoPickers must be members of the team in this sessionThe team's members
Tasks with no feature … go toDropdownYes—Not in this PI, In this PI — no team yet, the session's teams
Find a task to give to a team…Search, at least 2 characters, 8 resultsNo—The project's tasks
Team for a single taskDropdownYes—The session's teams
Team that keeps a shared taskDropdown (RTE)Before the merge—The teams that hold the task

Capacity under a team depends on the measure. For Story points and Value (money) the team sets its capacity on its own board at Team breakouts, and until then the line reads the team sets it on its board at Team breakouts. For Hours and Days it comes from the people's availability.


6. Why you would use it​

  • No work falls through. Planned work with no team lists every story that would otherwise be planned by nobody, by name, before the breakouts start.
  • No work is planned twice. A task on two boards is flagged and decided once, instead of being discovered at the merge.
  • Product owners own their scope. They pull their features themselves in the room, without waiting for the RTE to do it for them.
  • Load is visible at a glance. Each team's ring shows how much open work it has taken, in the same measure its capacity will be set in, so an overloaded team is obvious before planning.

7. Worked example​

The session PI 2026.4 Planning measures capacity in Story points. Five features are in scope — 21 stories — and no team holds any (Figure 1). Conflicts reads 5 features in the PI have no team; 21 open tasks would not be planned.

  1. At 09:00 on Day 1 Maya Fernandes starts Product / solution vision. Lena Hoffmann presents; the tab comes alive.
  2. Priya Sharma, Phoenix's product owner, drags Mobile Checkout 2.0 (23 SP, 5 stories) and Offline mode (21 SP, 3 stories) onto Phoenix.
  3. Marco Rossi takes UPI AutoPay mandates and Fraud scoring v2 for Atlas.
  4. Emma Clarke takes the enabler Observability platform (13 SP, 4 stories) for Orion.
  5. Features with no team reads Every feature in the PI has a team. Phoenix shows 8 open · 44 SP, Atlas 9 · 45 SP, Orion 4 · 13 SP, and Conflicts reads None (Figure 2).
  6. The 214 tasks without a feature stay Not in this PI.

When Maya starts Team breakouts, each board holds exactly its team's stories.


8. Before this works — what an administrator sets up​

NeededWithout it
Features in the project, and the PI's scope ticked in the session setupThis project has no features, or nothing under Features with no team
Teams with a product owner in Organization Settings → Planning TeamsPicks features reads the facilitator; only the RTE can place that team's features
Product owners holding Take part in a PI session as a team member: move cards on your own team's board, post, raise risks, propose cross-team dependencies, demo and vote.They see the board but cannot pick
A "Product / solution vision" briefing item in the agendaThe tab opens with the next switched-on item or the first planning item instead
Team members added to the project and able to open the sessionThe amber triangle on the team's members button counts them
Who picks, set in Roles & permissionsBy default product owners pick for their own team, and the Product Manager and System Architect for any team

Someone who may not pick sees the note You can see the allocation but not change it naming who can.


9. What it affects elsewhere​

PlaceEffect
Team boardsEach team's board holds the open tasks of its features, in the iterations and in the backlog
Team boards in the railShows the number of tasks that are on two boards
ART Planning BoardFeatures show under the team that plans them
Management reviewA feature with no team is listed as at risk; a scope change can move it

10. Don't confuse this with…​

ThisIs notBecause
Giving a feature to a teamAssigning a task to a personAssignment happens on the team board
Not in this PI hereThe PI's scope in the setupBoth change the scope; the setup's Scope step is the place before the event. See Create a session
Choose whoPlanning Teams rolesChoose who only lets members pick features in this session
Moving a feature in a planning adjustmentDragging it hereA scope change from management review is answered by the team and applied for it

11. Troubleshooting​

SymptomCause
A team has features but an empty board; a warning says tasks cannot reach the team boardsThe tasks are in a milestone outside this PI. See When tasks are outside the PI
Tasks moved into the PI do not appear on a boardThey arrive with Bring onto the boards, not by themselves
Nothing can be dragged; the intro ends Teams take their features when …The "Product / solution vision" item has not started yet
A team column shows a lock while you dragYou may only give features to teams you pick for
another team already plans that feature — ask the facilitator to move itA product owner cannot take a feature from another team
Capacity in shows as textPlanning has started; the measure is fixed
The task search shows nothingType at least two characters
A team's members button is amberMembers cannot use their board yet; open it for the reason
Planned work with no team stays after draggingA feature in the PI still has no team, or tasks without a feature are set to In this PI — no team yet
A task shows on two boardsA single-task override or a shared feature; the RTE picks the team under Conflicts
Conflicts lists a person in more than one teamA shared specialist; allowed. Their load from both teams counts against one capacity on the ART Planning Board