Final plan review

What this page is — the Final plan review tab on Day 2: each team presents its final plan to the room, one team at a time, and the Business Owners accept it or send it back.

What it is for — so the Business Owners see what changed overnight, what each team now commits to and what still threatens the plan, and give each team a clear yes or a clear "rework this" before the train votes.

The problem it solves — after a night of management adjustments and a second breakout, nobody in the room can tell what moved since the draft plans. Without a side-by-side view and an explicit acceptance, the confidence vote is taken on plans the Business Owners never agreed to, and the merge commits them anyway.

Route: /org/tasks/pi-planning?project=…&session=…&tab=final_review · Permission to view: Open PI Planning sessions read-only: brief, team boards, program board, risks, discussion, objectives and review. · Permission to run: Run a PI session: start, pause and end the timer, breaks, broadcasts, category allocation, conflicts, risk synthesis, restart and merge.


1. Draft plan, final plan​

Draft plan review (Day 1)Final plan review (Day 2)
ShowsThe plan as first draftedThe plan after management adjustments, against the Day 1 plan
Business valueNot scored yetScored by the Business Owners, with the change since Day 1
Ends withManagement reviewA Business Owner decision per team: Accept the plan or Send back
FeedsThe Management review's findingsThe ART risks session, the confidence vote and the merge

The final review has four parts for every team, in the order of the SAFe agenda: changes to capacity and load, final PI objectives with business value, ART PI risks and impediments, and Q&A.


2. A team on screen​

Figure 1 — Phoenix's final plan on screen, with the Business Owners' decision bar.
#ElementWhat it does
1Team tab with its chipOne team at a time; the chip shows its decision: Accepted, Sent back or Not reviewed. A green dot marks the team on everyone's screen
2Not reviewedNot reviewed yet — no Business Owner has decided on this plan
3Accepted so farHow many plans are accepted. Opens a summary of the accepted plans
4Baseline lineChanges are shown against the Day 1 plan. The Day 1 plan is saved automatically when the Draft plan review agenda item closes
5Save the plans as they are now insteadRe-baseline: save the plans as they are now. RTE only; replaces the saved Day 1 plan of every team
6Minutes per teamMinutes per team — the timer on the right counts down for the team on screen
7Business Owners:The Business Owners and their decisions, one chip per decision with a check or a return arrow; hover a chip for its note
8Accept the planAccept the plan
9Send backSend back — needs a note; the team returns to planning
101. Changes to capacity and loadSection 1 — what changed in load and capacity since Day 1, iteration by iteration, then the load chart and each iteration's goal

3. Objectives, risks and questions​

Figure 2 — Section 2: final objectives and how their business value changed since Day 1.
#ElementWhat it does
12. Final PI objectives with business valueSection 2 — the final objectives with the business value the Business Owners gave them
2Change chipsWhat changed in business value since Day 1: BV — → 10 means no value on Day 1, 10 now. A green chip is a new objective, a struck-through red chip one that was dropped
3Summary lineCommitted count, total planned business value, stretch count
Figure 3 — Section 3: ART-level risks and what the team is blocked by; section 4, Q&A, follows.
#ElementWhat it does
13. ART PI risks and impedimentsSection 3 — ART-level risks and what the team is blocked by. Only risks the team placed at ART level appear; they are ROAMed in the next agenda item
2Dependency stateDependencies now show whether the other team accepted them
3A question in 4. Q&AThe question and who asked it; the team types its answer under it and presses Answer. Challenges are noted here, not solved in this timebox
4Ask the team a question…Ask the team a question. Press the send icon

4. Step by step​

Before the item (RTE)​

  1. Check the baseline line. If the Day 1 plan was never saved — the Draft plan review was skipped — the line reads No Day 1 plan was saved and Save the plans as they are now saves one.
  2. Set Minutes per team. Without a value, the item's length is shared out among the teams, with at least five minutes each.

Present the plans​

  1. Start the Final plan review agenda item. The tab is closed until then: The final plan review opens on Day 2.
  2. Press Present. The first team goes on everyone's screen and its timer starts. Because you are management, the presentation is shared: everyone in the session is taken to this tab in Present mode and follows the team you show.
  3. Let the team talk through sections 1 to 4. Questions arrive in Q&A; the team or management answers.
  4. Move to the next team with the arrow buttons or keys. After the last team comes Accepted so far — the wall of accepted plans — and the room sees it too.
  5. Press End presenting (or leave full screen with Esc). The presentation ends for everyone.

The general rules of shared presentations — who may start one, the 4-hour limit, rejoining — are on Agenda.

Following the review (participants)​

While management presents, your screen shows the team on stage, or the Accepted so far wall, in Present mode. The arrows and End presenting are replaced by a badge Following with the presenter's name; only the presenter changes team. Leave presentation in the badge (tooltip Leave the presentation — you can rejoin from the banner) returns you to your own screen, for example to read another team's plan. Someone outside management who presses Present sees Present mode on their own screen only.

Figure 4 — A participant follows the final plan review: the team on screen is the presenter's.
#ElementWhat it does
1Following Maya Fernandes · Leave presentationShown instead of the arrows and End presenting while you follow; Leave presentation returns you to your own screen

Outside a presentation, participants see On screen now: Phoenix with Follow to jump to the team on screen.

Present mode​

Present fills the screen with the team on stage: the team strip, the team's final plan and its timer, without the rail and the header.

Figure 5 — Presenting Phoenix's final plan; all three plans are accepted, and Phoenix's time ran over.
#ElementWhat it does
1Team strip and Accepted so farEach team with its state (Accepted, Sent back, Not reviewed); click a team to put it on screen. Accepted so far · N/M opens a summary: how many plans are accepted, how many were sent back, and, if any were sent back, a pointer to the Plan rework agenda item
2Next team (→)Puts the next team on everyone's screen and starts its timer. After the last team comes Accepted so far. ← goes back. A participant following the presentation has no arrows
3The team's timeCounts down the minutes per team; when the time is used up it turns red with a + and counts the overrun
4Changes to capacity and loadEach iteration's load and capacity now, against the Day 1 plan, with the change, a chart against capacity and the focus target, and one card per iteration
5Final PI objectives with business valueThe committed objectives with the business value the Business Owners gave each, then the stretch objectives, which do not count in the committed value

Sections 3 (risks and dependencies) and 4 (Q&A) follow below on the same screen.

Decide on a plan (Business Owner, or the RTE for them)​

  1. Press Accept the plan or Send back. A drawer opens on the right.
  2. For Accept, a Note (optional). For Send back, What should the team rework? is required.
  3. Press Accept or Send back in the drawer.

The RTE's drawer says You record it for the Business Owners in the room, and the chip shows the RTE's name with (for the BOs).

The Send back drawer​

Figure 6 — Sending Phoenix's plan back, recorded by the RTE for the Business Owners.
#ElementWhat it does
1The drawerSend "team"'s plan back — the Business Owners' decision. Opened by the RTE, it reads You record it for the Business Owners in the room; a Business Owner deciding for themselves does not see that line
2What should the team rework?Required. The team sees it on its board in the Plan sent back banner, with who sent it back
3Send backRecords the decision. The plan no longer counts as presented until it is accepted. Greyed out until the note is typed; Cancel closes the drawer

5. Field reference​

ControlTypeRequiredValidationWho
Minutes per teamNumber fieldNo1 to 120Management: the RTE, the manage or facilitate permission, Product Manager, System Architect, Business Owners
Save the plans as they are now insteadLink—Asks nothing; replaces every team's Day 1 planThe RTE
Accept the plan noteMulti-line textNoUp to 2,000 charactersBusiness Owners and the RTE
What should the team rework?Multi-line textYes1 to 2,000 charactersBusiness Owners and the RTE
Ask the team a question…Single-line textYes, to send1 to 1,000 charactersAnyone in the session
Following badge · Leave presentationBadge with a link—Shown while someone in management presents and you have not leftEveryone following the presentation
The team's answer…Single-line textYes, to sendUp to 4,000 charactersMembers of that team, and management

Each Business Owner's decision is kept; the latest decision sets the plan's state. A plan sent back can be accepted later, and the chip changes to Accepted.

What each decision does​

DecisionThe planThe team's board
Accept the planCounts as presented for the confidence vote and the mergeNothing changes
Send backReturns to planning — no longer counted as presented until acceptedShows Plan sent back by … with the note

6. Why you would use it​

  • Overnight change becomes visible. The Day 1 baseline turns "we re-planned" into numbers: Phoenix's Iteration 3 load fell by 8 points when Offline mode was postponed.
  • Value and plan meet. The Business Owners see the business value they scored next to the load that delivers it.
  • A real acceptance gate. The confidence vote and the merge rely on plans someone with authority accepted, with a reason recorded when they did not.
  • Open questions are not lost. Q&A keeps challenges with the team they concern.

7. Worked example​

Day 2 of PI 2026.4 Planning; the agenda item Final plan review and lunch runs 11:00–13:00 and the session moves to Review — the header clock reads Review · the planning clock is stopped.

  1. Maya Fernandes sets Minutes per team to 15 and presses Present. Phoenix goes on screen — on hers and, with Following Maya Fernandes, on every participant's.
  2. Section 1 shows Iteration 1 at 11 SP against 10 SP, unchanged since Day 1 and still over capacity; Iteration 2 load -5 SP; Iteration 3 load -8 SP, the postponed Offline mode.
  3. Section 2 shows Shoppers pay with a saved card in one tap: BV — → 10 and 2 committed · planned business value 17 · 1 stretch.
  4. Section 3 shows no ART risk from Phoenix and two dependencies, on Atlas's device fingerprint signals and Orion's tracing, both (accepted).
  5. Sofia Alvarez presses Accept the plan, adds no note, and presses Accept. Phoenix's chip turns to Accepted.
  6. Orion is accepted next. Atlas goes on screen and is accepted too.
  7. Accepted so far reads 3 of 3 plans accepted, 0 sent back, the committed objectives and the planned business value of the whole train.

Had Sofia sent Atlas back with Fingerprints first — the mandate screen cannot fill Iteration 1, Atlas's board would show the note, and the RTE would see a reminder to switch on Plan rework (if needed) on the Agenda before the confidence vote.


8. Before this works — what an administrator sets up​

NeededWithout it
A switched-on agenda item whose title contains Final plan reviewThe tab opens with the Draft plan review instead, and the minutes default to 10 per team
A closed Draft plan review on Day 1No Day 1 plan, so section 1 shows the final plan only
Business Owners named for the sessionOnly the RTE can accept or send back
Objectives scored in Team breakout #2Section 2 shows — for business value
The Final plan review row for the role in Roles & permissions (every role has it by default)That role has no Final plan review tab, and cannot read the review or ask or decide on it

9. Downstream effects​

WhereWhat changes
ART risksThe risks named in section 3 are ROAMed in the next agenda item
Confidence voteAccepted plans count as presented
Plan reworkA sent-back team reworks there; the note is shown on its board
Post-PI PlanningThe merge takes the accepted plans

10. Don't confuse this with…​

ThisIs notBecause
Final plan reviewDraft plan reviewThe draft review shows the first plan and saves the Day 1 baseline; the final review compares against it and decides
Send backA low confidence voteSend back is one Business Owner's decision on one plan; the confidence vote is everyone's
Re-baselineUndoIt does not change any plan; it only moves the point the changes are measured from
Q&A hereQuestions on adjustmentsThose belong to one management adjustment. See Planning adjustments

11. Troubleshooting​

SymptomCause and fix
The final plan review opens on Day 2The Final plan review agenda item has not started
No Day 1 plan was savedThe Draft plan review item never closed. The RTE saves the plans now
Every change reads no change after a re-baselineThe baseline was saved after the adjustments. It cannot be restored
No Accept the plan buttonYou are neither a Business Owner nor the RTE, or the session is committed
Send back in the drawer stays greyed outThe rework note is required
No team to reviewYour role is not allowed to see the teams' plans
The Final plan review tab is missingThe project's rule book does not give your role the Final plan review row
Your screen changed team by itself and the arrows are goneSomeone in management is presenting and you follow. Press Leave presentation to look around on your own
You presented but nobody followedOnly management shares a presentation; anyone else's Present stays on their own screen
Someone else is presenting — they end it first, or the RTE takes over.Another manager is presenting. Wait until they end it; the RTE can end it for them
The header clock reads Review · the planning clock is stoppedThe review agenda items run while the session is in Review; the planning clock runs only in the breakouts and adjustment rounds. It is not an overrun
The timer shows a plus signThe team has run over its minutes
A team's chip is still Not reviewedNo Business Owner decided. Present it again and decide

What changed overnightPlanning adjustments
The value in section 2Objectives
What comes nextRisks and ROAM · Confidence vote