Confidence vote

What this page is — the Confidence vote tab of a PI session: a fist-of-five vote in two steps, first every team on its own plan, then everyone on the whole train's plan, with a live count, a heatmap and a place to decide what happens after a low score.

What it is for — turning "are we sure about this plan?" into a number per team and for the ART, and making sure every serious doubt is heard and either fixed or recorded as a risk before the plan is committed.

The problem it solves — without a structured vote, the loudest people in the room set the mood and the quiet engineer who knows the certification slot is not booked says nothing. Two weeks into the PI that doubt becomes a missed objective. The vote catches it while the teams are still in the room and can still change the plan.

Route: /org/tasks/pi-planning?session=…&tab=review · Permission to open: Open PI Planning sessions read-only: brief, team boards, program board, risks, discussion, objectives and review. · Permission to vote: Take part in a PI session as a team member: move cards on your own team's board, post, raise risks, propose cross-team dependencies, demo and vote. · Run the vote: the session's named facilitator (the RTE)


1. The idea: two votes, one commitment​

The vote sits on Day 2, after the Final plan review and once the ART risks have been ROAMed. Before anyone votes, the tab shows what a vote commits to — A commitment with two parts:

  1. Teams agree to do everything in their power to meet the agreed-to objectives.
  2. If objectives become not achievable, teams agree to escalate immediately so that corrective action can be taken.

Each person then shows a hand from 1 to 5 fingers:

ScoreLabel on the cardColourCounts as
1No confidenceRedLow — asks for a concern
2Little confidenceRedLow — asks for a concern
3Good confidenceAmberAcceptable
4High confidenceGreenAcceptable
5Very high confidenceGreenAcceptable

The vote runs in two steps, and they answer different questions:

Team voteART vote
The questionHow confident are you in Phoenix's plan?How confident are you in the whole ART's plan?
Who votesEach team's members, on their own team only, all teams at the same timeThe session's participants: team members, the RTE and the ART roles (Product Manager, System Architect, Business Owners)
Who does notAnyone outside the teamAnyone who only follows the session
x of y voted countsThe teams' membersAll the participants, so it never passes 100 %
What a low result triggersThat team reworks, or accepts the risks and moves aheadEvery team reworks, or the train accepts the risks and moves ahead
Who decides after a low resultThe team (a role with the Plan right) or the RTEThe RTE

An average under 3 is low confidence, shown as a red Low confidence badge. An average of 3 or more shows Good confidence in green.


2. Why you would use it​

  • Doubts surface while they are cheap. A concern raised at 14:00 on Day 2 costs an hour of rework; the same concern raised in Iteration 2 costs a missed objective.
  • Nobody is outvoted silently. Anyone voting 1 or 2 is asked for the concern in a sentence, and the RTE turns it into a tracked risk in one click — it does not stay a feeling in the room.
  • The room sees the result at once. Counts drop into five coloured columns as hands come in, so there is no counting of raised hands and no arguing about the average.
  • The decision is on record. Who decided to rework or move ahead, and why, is kept with the vote and carried to the team's board if it reworks.
  • A second vote round proves the fix. After a rework the train votes again, and the earlier vote round's average stays visible next to the new one.

3. Where it fits in the event​

BeforeThe voteAfter
Final plan review — Business Owners accept or send back each planTeam vote, then ART voteGood confidence → the retrospective, then the plan is committed in Post-PI Planning
Risks and ROAM — the ART risks are resolved, owned, accepted or mitigatedLow confidence → a decision per team or for the ARTRework → Plan rework, then a new vote round

The tab follows the Confidence vote item of the agenda. Closing that agenda item also closes any vote that is still open, so late hands cannot change the result.


4. The screen before the vote opens​

Figure 1 — The Confidence vote tab, as the RTE sees it with the vote not started.
#ElementWhat it does
1Step badgeWhere the vote is: Not started, ● Team vote open, ● ART vote open or Voting closed
2Open the team voteOpens the first step. Every team votes on its own plan, all teams at once
3Open the ART voteOpens the second step directly. Everyone votes on the whole train's plan
4Full screenEnlarges the tab for the room's screen. Exit full screen brings it back
5A commitment with two partsWhat a vote commits to. Read it aloud before opening the vote
6The ART vote panelA column per score (fist of five) with its count, the average and the verdict, and x of y voted
7Confidence heatmapA row per team: votes per score, Voted (votes / the team's members), Average and the verdict
8The whole ART rowThe ART vote in the same shape, in bold; its Voted counts against all the session's participants

A participant who is not the RTE sees The Release Train Engineer opens the vote when the ART risks are addressed. in place of the buttons.

When the vote is switched off​

A project can run PI Planning without a confidence vote. When Project settings → PI Planning has the Confidence vote switch off, every session of the project follows it at once:

WhatWith the switch off
The Confidence vote tabNot in the rail, for anyone, including the RTE
The Confidence vote agenda itemSwitched off if it has not started, so the agenda run skips it. An item that already ran keeps its place
New agendasThe SAFe two-day and distributed split agendas, and switching an existing agenda to one of them, leave the Confidence vote item switched off
VotingNot possible: an attempt answers The confidence vote is switched off for this project (Project settings → PI Planning).
Figure 2 — With the project's Confidence vote switched off, the session has no Confidence vote tab.
#ElementWhat it does
1Retrospective follows ObjectivesThe Confidence vote tab is gone from the rail while the project switch is off; it comes back when the switch is turned on again

The rest of the event is unchanged: the Final plan review still records accepted and sent-back plans, and the plans are merged and committed in Post-PI Planning as usual. To use the vote, a project manager switches it on in project PI Planning settings; the tab comes back at once, and a Confidence vote item that only the switch had turned off is on again. An item an agenda was created without (switched off in the agenda itself) stays off until it is switched on in the Agenda.


5. Step by step​

Run the team vote (the RTE)​

  1. Open the Confidence vote tab, or start the Confidence vote agenda item, which opens it.
  2. Read the two-part commitment to the room.
  3. Press Open the team vote. The badge turns to ● Team vote open.
  4. Watch x of y voted until every team has voted.

Cast your vote (a team member)​

Figure 3 — A participant's ballot during the team vote.
#ElementWhat it does
1● Team vote openThe team step is open; your ballot is live
2The questionHow confident are you in your team's plan? — you vote on your own team only. Someone in two teams gets a ballot per team
3The hand cards1 — No confidence … 5 — Very high confidence. One press records the vote
4A low scoreChoosing 1 or 2 opens a field: What worries you? Say it — it can become a risk.
5Team votes, liveEvery team's columns fill as votes come in. While the vote is open you see counts only
6Names show once the vote is closedWho voted what stays hidden until the RTE closes the step
  1. Press the hand that matches your confidence. A confirmation reads You voted 4.
  2. If you chose 1 or 2, type your concern and press Send concern. A concern is up to 2,000 characters.
  3. Changed your mind? Press another hand while the vote is open; your last choice counts.
Figure 4 — After voting: your own hand shows with your initials; everyone else's stays anonymous until the step closes.

Close the team vote and open the ART vote (the RTE)​

Figure 5 — The RTE's live view of the team vote. Atlas averages 2.6, under the line of 3.
#ElementWhat it does
1Close it — open the ART voteCloses the team step (names now show on the team votes) and opens the ART step
2Close votingCloses the vote altogether, without an ART step
3x of y votedTeam votes cast against the number of team members. In the ART step the same line counts against every participant
4A team and its averageAtlas · 2.6 — below 3, so Atlas will appear under Low confidence once the step closes

The ART vote and a low result​

Figure 6 — The ART vote open, with Atlas's low team result waiting for a decision.
#ElementWhat it does
1● ART vote openThe second step is open
2Team vote again · Close votingRe-open the team step (votes already cast are kept and can be changed), or close voting
3The ART questionEveryone votes on the whole ART's plan
4You voted 4Your vote; tap another hand to change it while the vote is open
516 of 20 votedART votes cast against every participant. Beside The ART vote heading: the live average, the verdict (Good confidence at 3 or above, Low confidence under 3) and the five columns
6Low confidence panelAppears for any team or the ART whose step is closed with an average under 3: hear the concerns, then rework the plan or accept the risks and move ahead
7Raise as a riskThe RTE turns that voter's concern into a risk. The button then reads Raised as a risk and opens the Risks tab
8Rework the planRecords a rework decision for that team, with the optional note; it then shows Rework the plan, who decided and the note
9Accept the risks and move aheadRecords the opposite decision; it then shows Risks accepted — moving ahead, who decided and the note
  1. Press Close it — open the ART vote. Everyone with a vote sees the ART question.
  2. While the ART vote runs, read out the concerns in the Low confidence panel for any team that scored under 3.
  3. For each concern worth tracking, press Raise as a risk.
  4. Have the team, or decide yourself, for each low result: type a note and press Rework the plan or Accept the risks and move ahead. A message confirms Plan rework chosen or Risks accepted — moving ahead.
  5. Press Close voting when the ART vote is in. The names now show on every hand.

After the decision​

Figure 7 — A team to rework, and the heatmap that explains why.
#ElementWhat it does
1Plan rework (if needed)The teams that will rework and why. It appears as soon as a decision says rework, or a plan was sent back in the Final plan review
2Start Plan reworkSwitches the Plan rework agenda item on and starts it. See Plan rework
3A team to reworkIts average, the decision's note and the low voters' concerns; to rework until the rework starts
4The heatmapVotes per score per team, Voted, Average
5The verdictPer team and for the whole ART

Start the plan rework​

Start Plan rework sits at the top right of the Plan rework (if needed) panel, for the RTE only, until the rework has started. It asks first.

Figure 8 — The confirmation before the plan rework starts.
#ElementWhat it does
1Start the reworkStarts the rework — the Plan rework agenda item is switched on and started, the team boards reopen, and everyone in the session is taken to them. Cancel or the cross leaves everything as it is

The message names the teams to rework: those whose decision says Rework the plan and those whose plan was sent back in the Final plan review. Once it has started, the panel header reads Plan rework — under way since the time, and the button gives way to Start vote round 2 now (or Every team is ready — start vote round 2 when every team has said it is ready).

After a rework, the RTE starts the next vote round. The heatmap title then reads Confidence heatmap · vote round 2, and the earlier averages stay underneath.

Figure 9 — Vote round 2 closed: the train is confident and the next step is shown.
#ElementWhat it does
1The vote roundConfidence vote — vote round 2
2Voting closedNames now show on the cards; hover a hand to see the voter and any concern
3The verdictThe ART stands by its plan — 4.2 average. when the ART vote is 3 or more
4Next stepThe train is confident. Commit the plan in Post-PI Planning after the retrospective. (the RTE only)
5Earlier vote roundsEarlier: vote round 1 — ART 3.8
6Planning round 3The session's planning round, which the rework moved on. It counts planning rounds, not vote rounds

6. Field and control reference​

ControlTypeWhoRules
Hand cards 1–5Single choice, one pressTeam step: members of that team. ART step: the session's participants — team members, the RTE, the ART rolesOnly while that step is open, the session is running and the project's Confidence vote switch is on. Pressing again replaces your vote
Your concernOne-line text, optionalThe voter, after choosing 1 or 2Up to 2,000 characters. Send concern is greyed out while it is empty
Open the team vote / Team vote againButtonThe RTEOpens the team step. Votes of the current round are kept
Open the ART vote / Close it — open the ART vote / ART vote againButtonThe RTEOpens the ART step and closes the team step
Close votingButtonThe RTECloses whichever step is open. Closing the agenda item does the same
Raise as a riskButtonThe RTEOnly on a vote of 1 or 2 that carries a concern, once per vote. Title = the concern (cut at 200 characters)
NoteOne-line text, optionalWhoever decidesUp to 2,000 characters, shown beside the decision and on the team's rework banner
Rework the plan / Accept the risks and move aheadButtonsTeam result: the RTE, or a member of that team whose role has the Plan right. ART result: the RTEOne decision per team per vote round, kept until the next vote round starts
Start vote round N now / Every team is ready — start vote round NButtonThe RTEOnly during a plan rework. Starts the next vote round

Where the values come from: the voter lists are the teams chosen for the session and their members; the ART roles come from the session's ART roles. In the team step, y in x of y voted is the teams' members. In the ART step, y is every participant of the session — the teams' members, the RTE, the Product Manager, the System Architect and the Business Owners, each counted once — so the count never passes 100 %. Only those participants can vote in the ART step; anyone else is told Only the people taking part in the session (the teams, the RTE and the ART roles) can do this.

A concern raised from a team vote becomes that team's risk placed at ART level; a concern from the ART vote becomes a programme-level risk. Either way it appears on the Risks tab with the description Raised from the confidence vote (a 2): ….


7. Worked example — PI 2026.4​

  1. At 14:00 on Day 2 Maya Fernandes starts the Confidence vote agenda item and presses Open the team vote.
  2. Arjun Rao presses 4 on How confident are you in Phoenix's plan?. His initials appear in Phoenix's 4 column; everyone else's hands are plain dots.
  3. Aisha Bello and Hana Suzuki of Atlas vote 2 and type Certification slot still open and Fraud model needs labelled data we do not have. Three Atlas members vote 3. Atlas averages 2.6; Phoenix 4.0; Orion 4.4. The counter reads 15 of 15 voted — the three teams' fifteen members.
  4. Maya presses Close it — open the ART vote. The Low confidence panel appears for Atlas with both concerns.
  5. Aisha, as Atlas's scrum master, types Move fraud scoring stories later and add the certification fallback. and presses Rework the plan. Maya leaves both Raise as a risk buttons alone: the NPCI certification risk is already on the Risks tab, owned by Marco Rossi, and the fraud-data concern is one the rework itself will answer.
  6. The ART votes: five 3s, nine 4s, two 5s — 3.8, 16 of 20 voted. The twenty are the fifteen team members plus Maya, Lena Hoffmann, Kenji Watanabe, Sofia Alvarez and David Okafor. Maya presses Close voting.
  7. The Plan rework (if needed) panel lists Atlas. Maya presses Start Plan rework and the train moves to Plan rework.
  8. After the rework Maya presses Every team is ready — start vote round 2. Every team votes again: Phoenix 4.2, Atlas 3.8, Orion 4.4, and the ART 4.2 — twelve 4s and three 5s, 15 of 20 voted. The tab reads The ART stands by its plan — 4.2 average., with Earlier: vote round 1 — ART 3.8 under the heatmap. The session bar meanwhile reads Planning round 3: the rework added a planning round, the vote its own vote round.

8. The admin contract​

Must be in placeWhereWhat happens without it
The Confidence vote switch is onProject settings → PI Planning (see project PI Planning settings)No Confidence vote tab, the agenda item is switched off if it has not started, and nobody can vote
The Confidence vote row for the role in Roles & permissionsThe rule bookThat role has no Confidence vote tab
Teams with members are chosen for the sessionCreate a sessionA team with no members has nothing to vote; a team's y is its member count
A named facilitatorThe sessionNobody can open, close or reset the vote
Voters are members of the session's teamsPlanning teamsSomeone in no team cannot vote on a team's plan; in the ART step only the RTE and the ART roles vote besides team members
The Plan right on the team roles that should decideRoles & permissionsOnly the RTE can record the team's decision
The ART roles named on the sessionSession setupThe Product Manager, System Architect and Business Owners are not participants: they cannot vote in the ART step and are not counted in its y

The project setting's own hint still describes a single vote at review. The tab it controls is the two-step vote described on this page.


9. What it changes elsewhere​

  • Risks — every Raise as a risk adds a risk on the Risks tab, to be ROAMed like any other.
  • Plan rework — a Rework the plan decision puts the team (or, for the ART, every team) on the Plan rework list and later shows the reasons on the team's board.
  • Post-PI Planning — a confident ART vote points the RTE to Post-PI Planning, where the plan is committed.
  • Nothing reaches the live tasks. The vote changes no task, iteration or estimate.

10. Don't confuse this with…​

ThisIs notBecause
The confidence voteThe Final plan reviewThere, Business Owners accept or send back a team's plan. Here, the people doing the work say how confident they are
Raise as a riskRaising a risk on the Risks tabThe button copies a voter's concern; the Risks tab is where it is then owned and ROAMed
Rework the planAn adjustment round of Planning adjustmentsManagement adjustments respond to the Day 1 review; a rework responds to a low vote. Both reopen the boards
Vote roundsPlanning roundsPlanning round 3 in the session bar counts planning rounds (Day 1's breakouts, then each adjustment round); vote round 2 in the vote title counts vote rounds. Hover the session bar's label for the explanation
Accept the risks and move aheadAccepted in ROAMThe decision records that the team (or train) goes ahead despite low confidence; ROAMing a single risk as Accepted happens on the Risks tab

11. Troubleshooting​

SymptomCauseWhat to do
The teams vote on their own plans now. The ART vote follows. and no ballotYou are in no team of the sessionWait for the ART step, or ask the RTE to add you to a team
Only the people taking part in this session vote — the teams, the RTE and the ART roles. during the ART stepYou are in no team of the session, not the RTE and not named as an ART role (PM, SA, business owner)Ask the RTE to name you as an ART role or add you to a team
Only the people taking part in the session (the teams, the RTE and the ART roles) can do this.You pressed a hand in the ART step but are not a participant — for example you hold the manage permission but no team or ART roleAsk the RTE to name you as an ART role or add you to a team
The ART counter reads fewer votes than people in the roomIts y is every participant: the teams' members, the RTE and the ART rolesNothing; people who have not voted yet can still vote while the step is open
No names on the cardsThe step is still openNames appear once the RTE closes that step
No Raise as a risk button on a low voteThe voter wrote no concern, or it was already raised, or you are not the RTEAsk the voter to send a concern; a raised one reads Raised as a risk
No decision buttons for my teamYour role lacks the Plan right, or a decision is already recorded for this roundAsk the RTE to decide, or to change the rule book
Late votes stopped being acceptedThe Confidence vote agenda item was closed, which closes votingThe RTE presses Team vote again or ART vote again
No Confidence vote tab in the railThe project's Confidence vote setting is off, or the rule book does not give your role the Confidence vote rowA project manager switches it on in Project settings → PI Planning, or changes the rule book
The confidence vote is switched off for this project (Project settings → PI Planning).The setting was switched off while you had the tab openReload the page; switch the setting on to vote
The Confidence vote agenda item shows switched offThe project's setting is off and the item had not startedSwitch the setting on; the item comes back
The header clock reads Review · the planning clock is stoppedThe vote runs while the session is in Review; the planning clock runs only in the breakouts and adjustment roundsNothing; it is not an overrun