Confidence vote
What this page is — the Confidence vote tab of a PI session: a fist-of-five vote in two steps, first every team on its own plan, then everyone on the whole train's plan, with a live count, a heatmap and a place to decide what happens after a low score.
What it is for — turning "are we sure about this plan?" into a number per team and for the ART, and making sure every serious doubt is heard and either fixed or recorded as a risk before the plan is committed.
The problem it solves — without a structured vote, the loudest people in the room set the mood and the quiet engineer who knows the certification slot is not booked says nothing. Two weeks into the PI that doubt becomes a missed objective. The vote catches it while the teams are still in the room and can still change the plan.
Route: /org/tasks/pi-planning?session=…&tab=review · Permission to open: Open PI Planning
sessions read-only: brief, team boards, program board, risks, discussion, objectives and review. ·
Permission to vote: Take part in a PI session as a team member: move cards on your own team's
board, post, raise risks, propose cross-team dependencies, demo and vote. · Run the vote: the
session's named facilitator (the RTE)
1. The idea: two votes, one commitment
The vote sits on Day 2, after the Final plan review and once the ART risks have been ROAMed. Before anyone votes, the tab shows what a vote commits to — A commitment with two parts:
- Teams agree to do everything in their power to meet the agreed-to objectives.
- If objectives become not achievable, teams agree to escalate immediately so that corrective action can be taken.
Each person then shows a hand from 1 to 5 fingers:
| Score | Label on the card | Colour | Counts as |
|---|---|---|---|
| 1 | No confidence | Red | Low — asks for a concern |
| 2 | Little confidence | Red | Low — asks for a concern |
| 3 | Good confidence | Amber | Acceptable |
| 4 | High confidence | Green | Acceptable |
| 5 | Very high confidence | Green | Acceptable |
The vote runs in two steps, and they answer different questions:
| Team vote | ART vote | |
|---|---|---|
| The question | How confident are you in Phoenix's plan? | How confident are you in the whole ART's plan? |
| Who votes | Each team's members, on their own team only, all teams at the same time | The session's participants: team members, the RTE and the ART roles (Product Manager, System Architect, Business Owners) |
| Who does not | Anyone outside the team | Anyone who only follows the session |
| x of y voted counts | The teams' members | All the participants, so it never passes 100 % |
| What a low result triggers | That team reworks, or accepts the risks and moves ahead | Every team reworks, or the train accepts the risks and moves ahead |
| Who decides after a low result | The team (a role with the Plan right) or the RTE | The RTE |
An average under 3 is low confidence, shown as a red Low confidence badge. An average of 3 or more shows Good confidence in green.
2. Why you would use it
- Doubts surface while they are cheap. A concern raised at 14:00 on Day 2 costs an hour of rework; the same concern raised in Iteration 2 costs a missed objective.
- Nobody is outvoted silently. Anyone voting 1 or 2 is asked for the concern in a sentence, and the RTE turns it into a tracked risk in one click — it does not stay a feeling in the room.
- The room sees the result at once. Counts drop into five coloured columns as hands come in, so there is no counting of raised hands and no arguing about the average.
- The decision is on record. Who decided to rework or move ahead, and why, is kept with the vote and carried to the team's board if it reworks.
- A second vote round proves the fix. After a rework the train votes again, and the earlier vote round's average stays visible next to the new one.
3. Where it fits in the event
| Before | The vote | After |
|---|---|---|
| Final plan review — Business Owners accept or send back each plan | Team vote, then ART vote | Good confidence → the retrospective, then the plan is committed in Post-PI Planning |
| Risks and ROAM — the ART risks are resolved, owned, accepted or mitigated | Low confidence → a decision per team or for the ART | Rework → Plan rework, then a new vote round |
The tab follows the Confidence vote item of the agenda. Closing that agenda item also closes any vote that is still open, so late hands cannot change the result.
4. The screen before the vote opens
| # | Element | What it does |
|---|---|---|
| 1 | Step badge | Where the vote is: Not started, ● Team vote open, ● ART vote open or Voting closed |
| 2 | Open the team vote | Opens the first step. Every team votes on its own plan, all teams at once |
| 3 | Open the ART vote | Opens the second step directly. Everyone votes on the whole train's plan |
| 4 | Full screen | Enlarges the tab for the room's screen. Exit full screen brings it back |
| 5 | A commitment with two parts | What a vote commits to. Read it aloud before opening the vote |
| 6 | The ART vote panel | A column per score (fist of five) with its count, the average and the verdict, and x of y voted |
| 7 | Confidence heatmap | A row per team: votes per score, Voted (votes / the team's members), Average and the verdict |
| 8 | The whole ART row | The ART vote in the same shape, in bold; its Voted counts against all the session's participants |
A participant who is not the RTE sees The Release Train Engineer opens the vote when the ART risks are addressed. in place of the buttons.
When the vote is switched off
A project can run PI Planning without a confidence vote. When Project settings → PI Planning has the Confidence vote switch off, every session of the project follows it at once:
| What | With the switch off |
|---|---|
| The Confidence vote tab | Not in the rail, for anyone, including the RTE |
| The Confidence vote agenda item | Switched off if it has not started, so the agenda run skips it. An item that already ran keeps its place |
| New agendas | The SAFe two-day and distributed split agendas, and switching an existing agenda to one of them, leave the Confidence vote item switched off |
| Voting | Not possible: an attempt answers The confidence vote is switched off for this project (Project settings → PI Planning). |
| # | Element | What it does |
|---|---|---|
| 1 | Retrospective follows Objectives | The Confidence vote tab is gone from the rail while the project switch is off; it comes back when the switch is turned on again |
The rest of the event is unchanged: the Final plan review still records accepted and sent-back plans, and the plans are merged and committed in Post-PI Planning as usual. To use the vote, a project manager switches it on in project PI Planning settings; the tab comes back at once, and a Confidence vote item that only the switch had turned off is on again. An item an agenda was created without (switched off in the agenda itself) stays off until it is switched on in the Agenda.
5. Step by step
Run the team vote (the RTE)
- Open the Confidence vote tab, or start the Confidence vote agenda item, which opens it.
- Read the two-part commitment to the room.
- Press Open the team vote. The badge turns to ● Team vote open.
- Watch x of y voted until every team has voted.
Cast your vote (a team member)
| # | Element | What it does |
|---|---|---|
| 1 | ● Team vote open | The team step is open; your ballot is live |
| 2 | The question | How confident are you in your team's plan? — you vote on your own team only. Someone in two teams gets a ballot per team |
| 3 | The hand cards | 1 — No confidence … 5 — Very high confidence. One press records the vote |
| 4 | A low score | Choosing 1 or 2 opens a field: What worries you? Say it — it can become a risk. |
| 5 | Team votes, live | Every team's columns fill as votes come in. While the vote is open you see counts only |
| 6 | Names show once the vote is closed | Who voted what stays hidden until the RTE closes the step |
- Press the hand that matches your confidence. A confirmation reads You voted 4.
- If you chose 1 or 2, type your concern and press Send concern. A concern is up to 2,000 characters.
- Changed your mind? Press another hand while the vote is open; your last choice counts.
Close the team vote and open the ART vote (the RTE)
| # | Element | What it does |
|---|---|---|
| 1 | Close it — open the ART vote | Closes the team step (names now show on the team votes) and opens the ART step |
| 2 | Close voting | Closes the vote altogether, without an ART step |
| 3 | x of y voted | Team votes cast against the number of team members. In the ART step the same line counts against every participant |
| 4 | A team and its average | Atlas · 2.6 — below 3, so Atlas will appear under Low confidence once the step closes |
The ART vote and a low result
| # | Element | What it does |
|---|---|---|
| 1 | ● ART vote open | The second step is open |
| 2 | Team vote again · Close voting | Re-open the team step (votes already cast are kept and can be changed), or close voting |
| 3 | The ART question | Everyone votes on the whole ART's plan |
| 4 | You voted 4 | Your vote; tap another hand to change it while the vote is open |
| 5 | 16 of 20 voted | ART votes cast against every participant. Beside The ART vote heading: the live average, the verdict (Good confidence at 3 or above, Low confidence under 3) and the five columns |
| 6 | Low confidence panel | Appears for any team or the ART whose step is closed with an average under 3: hear the concerns, then rework the plan or accept the risks and move ahead |
| 7 | Raise as a risk | The RTE turns that voter's concern into a risk. The button then reads Raised as a risk and opens the Risks tab |
| 8 | Rework the plan | Records a rework decision for that team, with the optional note; it then shows Rework the plan, who decided and the note |
| 9 | Accept the risks and move ahead | Records the opposite decision; it then shows Risks accepted — moving ahead, who decided and the note |
- Press Close it — open the ART vote. Everyone with a vote sees the ART question.
- While the ART vote runs, read out the concerns in the Low confidence panel for any team that scored under 3.
- For each concern worth tracking, press Raise as a risk.
- Have the team, or decide yourself, for each low result: type a note and press Rework the plan or Accept the risks and move ahead. A message confirms Plan rework chosen or Risks accepted — moving ahead.
- Press Close voting when the ART vote is in. The names now show on every hand.
After the decision
| # | Element | What it does |
|---|---|---|
| 1 | Plan rework (if needed) | The teams that will rework and why. It appears as soon as a decision says rework, or a plan was sent back in the Final plan review |
| 2 | Start Plan rework | Switches the Plan rework agenda item on and starts it. See Plan rework |
| 3 | A team to rework | Its average, the decision's note and the low voters' concerns; to rework until the rework starts |
| 4 | The heatmap | Votes per score per team, Voted, Average |
| 5 | The verdict | Per team and for the whole ART |
Start the plan rework
Start Plan rework sits at the top right of the Plan rework (if needed) panel, for the RTE only, until the rework has started. It asks first.
| # | Element | What it does |
|---|---|---|
| 1 | Start the rework | Starts the rework — the Plan rework agenda item is switched on and started, the team boards reopen, and everyone in the session is taken to them. Cancel or the cross leaves everything as it is |
The message names the teams to rework: those whose decision says Rework the plan and those whose plan was sent back in the Final plan review. Once it has started, the panel header reads Plan rework — under way since the time, and the button gives way to Start vote round 2 now (or Every team is ready — start vote round 2 when every team has said it is ready).
After a rework, the RTE starts the next vote round. The heatmap title then reads Confidence heatmap · vote round 2, and the earlier averages stay underneath.
| # | Element | What it does |
|---|---|---|
| 1 | The vote round | Confidence vote — vote round 2 |
| 2 | Voting closed | Names now show on the cards; hover a hand to see the voter and any concern |
| 3 | The verdict | The ART stands by its plan — 4.2 average. when the ART vote is 3 or more |
| 4 | Next step | The train is confident. Commit the plan in Post-PI Planning after the retrospective. (the RTE only) |
| 5 | Earlier vote rounds | Earlier: vote round 1 — ART 3.8 |
| 6 | Planning round 3 | The session's planning round, which the rework moved on. It counts planning rounds, not vote rounds |
6. Field and control reference
| Control | Type | Who | Rules |
|---|---|---|---|
| Hand cards 1–5 | Single choice, one press | Team step: members of that team. ART step: the session's participants — team members, the RTE, the ART roles | Only while that step is open, the session is running and the project's Confidence vote switch is on. Pressing again replaces your vote |
| Your concern | One-line text, optional | The voter, after choosing 1 or 2 | Up to 2,000 characters. Send concern is greyed out while it is empty |
| Open the team vote / Team vote again | Button | The RTE | Opens the team step. Votes of the current round are kept |
| Open the ART vote / Close it — open the ART vote / ART vote again | Button | The RTE | Opens the ART step and closes the team step |
| Close voting | Button | The RTE | Closes whichever step is open. Closing the agenda item does the same |
| Raise as a risk | Button | The RTE | Only on a vote of 1 or 2 that carries a concern, once per vote. Title = the concern (cut at 200 characters) |
| Note | One-line text, optional | Whoever decides | Up to 2,000 characters, shown beside the decision and on the team's rework banner |
| Rework the plan / Accept the risks and move ahead | Buttons | Team result: the RTE, or a member of that team whose role has the Plan right. ART result: the RTE | One decision per team per vote round, kept until the next vote round starts |
| Start vote round N now / Every team is ready — start vote round N | Button | The RTE | Only during a plan rework. Starts the next vote round |
Where the values come from: the voter lists are the teams chosen for the session and their members; the ART roles come from the session's ART roles. In the team step, y in x of y voted is the teams' members. In the ART step, y is every participant of the session — the teams' members, the RTE, the Product Manager, the System Architect and the Business Owners, each counted once — so the count never passes 100 %. Only those participants can vote in the ART step; anyone else is told Only the people taking part in the session (the teams, the RTE and the ART roles) can do this.
A concern raised from a team vote becomes that team's risk placed at ART level; a concern from the ART vote becomes a programme-level risk. Either way it appears on the Risks tab with the description Raised from the confidence vote (a 2): ….
7. Worked example — PI 2026.4
- At 14:00 on Day 2 Maya Fernandes starts the Confidence vote agenda item and presses Open the team vote.
- Arjun Rao presses 4 on How confident are you in Phoenix's plan?. His initials appear in Phoenix's 4 column; everyone else's hands are plain dots.
- Aisha Bello and Hana Suzuki of Atlas vote 2 and type Certification slot still open and Fraud model needs labelled data we do not have. Three Atlas members vote 3. Atlas averages 2.6; Phoenix 4.0; Orion 4.4. The counter reads 15 of 15 voted — the three teams' fifteen members.
- Maya presses Close it — open the ART vote. The Low confidence panel appears for Atlas with both concerns.
- Aisha, as Atlas's scrum master, types Move fraud scoring stories later and add the certification fallback. and presses Rework the plan. Maya leaves both Raise as a risk buttons alone: the NPCI certification risk is already on the Risks tab, owned by Marco Rossi, and the fraud-data concern is one the rework itself will answer.
- The ART votes: five 3s, nine 4s, two 5s — 3.8, 16 of 20 voted. The twenty are the fifteen team members plus Maya, Lena Hoffmann, Kenji Watanabe, Sofia Alvarez and David Okafor. Maya presses Close voting.
- The Plan rework (if needed) panel lists Atlas. Maya presses Start Plan rework and the train moves to Plan rework.
- After the rework Maya presses Every team is ready — start vote round 2. Every team votes again: Phoenix 4.2, Atlas 3.8, Orion 4.4, and the ART 4.2 — twelve 4s and three 5s, 15 of 20 voted. The tab reads The ART stands by its plan — 4.2 average., with Earlier: vote round 1 — ART 3.8 under the heatmap. The session bar meanwhile reads Planning round 3: the rework added a planning round, the vote its own vote round.
8. The admin contract
| Must be in place | Where | What happens without it |
|---|---|---|
| The Confidence vote switch is on | Project settings → PI Planning (see project PI Planning settings) | No Confidence vote tab, the agenda item is switched off if it has not started, and nobody can vote |
| The Confidence vote row for the role in Roles & permissions | The rule book | That role has no Confidence vote tab |
| Teams with members are chosen for the session | Create a session | A team with no members has nothing to vote; a team's y is its member count |
| A named facilitator | The session | Nobody can open, close or reset the vote |
| Voters are members of the session's teams | Planning teams | Someone in no team cannot vote on a team's plan; in the ART step only the RTE and the ART roles vote besides team members |
| The Plan right on the team roles that should decide | Roles & permissions | Only the RTE can record the team's decision |
| The ART roles named on the session | Session setup | The Product Manager, System Architect and Business Owners are not participants: they cannot vote in the ART step and are not counted in its y |
The project setting's own hint still describes a single vote at review. The tab it controls is the two-step vote described on this page.
9. What it changes elsewhere
- Risks — every Raise as a risk adds a risk on the Risks tab, to be ROAMed like any other.
- Plan rework — a Rework the plan decision puts the team (or, for the ART, every team) on the Plan rework list and later shows the reasons on the team's board.
- Post-PI Planning — a confident ART vote points the RTE to Post-PI Planning, where the plan is committed.
- Nothing reaches the live tasks. The vote changes no task, iteration or estimate.
10. Don't confuse this with…
| This | Is not | Because |
|---|---|---|
| The confidence vote | The Final plan review | There, Business Owners accept or send back a team's plan. Here, the people doing the work say how confident they are |
| Raise as a risk | Raising a risk on the Risks tab | The button copies a voter's concern; the Risks tab is where it is then owned and ROAMed |
| Rework the plan | An adjustment round of Planning adjustments | Management adjustments respond to the Day 1 review; a rework responds to a low vote. Both reopen the boards |
| Vote rounds | Planning rounds | Planning round 3 in the session bar counts planning rounds (Day 1's breakouts, then each adjustment round); vote round 2 in the vote title counts vote rounds. Hover the session bar's label for the explanation |
| Accept the risks and move ahead | Accepted in ROAM | The decision records that the team (or train) goes ahead despite low confidence; ROAMing a single risk as Accepted happens on the Risks tab |
11. Troubleshooting
| Symptom | Cause | What to do |
|---|---|---|
| The teams vote on their own plans now. The ART vote follows. and no ballot | You are in no team of the session | Wait for the ART step, or ask the RTE to add you to a team |
| Only the people taking part in this session vote — the teams, the RTE and the ART roles. during the ART step | You are in no team of the session, not the RTE and not named as an ART role (PM, SA, business owner) | Ask the RTE to name you as an ART role or add you to a team |
| Only the people taking part in the session (the teams, the RTE and the ART roles) can do this. | You pressed a hand in the ART step but are not a participant — for example you hold the manage permission but no team or ART role | Ask the RTE to name you as an ART role or add you to a team |
| The ART counter reads fewer votes than people in the room | Its y is every participant: the teams' members, the RTE and the ART roles | Nothing; people who have not voted yet can still vote while the step is open |
| No names on the cards | The step is still open | Names appear once the RTE closes that step |
| No Raise as a risk button on a low vote | The voter wrote no concern, or it was already raised, or you are not the RTE | Ask the voter to send a concern; a raised one reads Raised as a risk |
| No decision buttons for my team | Your role lacks the Plan right, or a decision is already recorded for this round | Ask the RTE to decide, or to change the rule book |
| Late votes stopped being accepted | The Confidence vote agenda item was closed, which closes voting | The RTE presses Team vote again or ART vote again |
| No Confidence vote tab in the rail | The project's Confidence vote setting is off, or the rule book does not give your role the Confidence vote row | A project manager switches it on in Project settings → PI Planning, or changes the rule book |
| The confidence vote is switched off for this project (Project settings → PI Planning). | The setting was switched off while you had the tab open | Reload the page; switch the setting on to vote |
| The Confidence vote agenda item shows switched off | The project's setting is off and the item had not started | Switch the setting on; the item comes back |
| The header clock reads Review · the planning clock is stopped | The vote runs while the session is in Review; the planning clock runs only in the breakouts and adjustment rounds | Nothing; it is not an overrun |