Team board views

What this page is — a guide to the controls above a PI team board that change how the board is laid out: the nine Plan by views, Group by lanes, Card fields, the Filters row, Find a task… and the person picker.

What it is for — asking the board one question at a time. The same stories can be laid out by iteration, by person, by size, by feature, by milestone or by dependency, and in most views dragging a card answers the question: who does it, how big it is, which feature it belongs to.

The problem it solves — a board that only shows iterations hides half of the plan. A team sees that Iteration 1 is over capacity but not that Chen Wei carries most of it, that three stories are still unsized, or that a feature contributes to no milestone. Without other views the team discovers those gaps at the draft plan review, in front of management.

Route: Orbit Ops → PI Planning → open a session → Team boards → the Plan by row above the board · Permission to view: Open PI Planning sessions read-only: brief, team boards, program board, risks, discussion, objectives and review. · Permission to change a view: Take part in a PI session as a team member: move cards on your own team's board, post, raise risks, propose cross-team dependencies, demo and vote., plus the matching right in the project's rule book


1. The views at a glance​

Plan by decides what the columns are. The cards are always the same stories of the same team; only the question changes. The first four views are underlined in the colours of the strip along the top of each card (green assigned, blue sized, purple in a feature, yellow in an iteration), so a grey segment on a card tells you which view fixes it.

Plan byOne column perDragging a card into a columnRight it needs in the rule book
IterationsIteration of the PI, plus BacklogPlans the story into that iteration (or back to the backlog)Plan into iterations
ResourcePerson of the team, plus UnassignedAssigns the story to that personAssign people
SizeValue of the scale, plus Not sizedEstimates the storySize stories
FeatureFeature of the project, plus No featureMoves the story to that featureChange a story's feature
TypeTask type, plus No typeNothing — read only—
PriorityPriority, plus No priorityNothing — read only—
StatusLive task statusNothing — read only—
MilestoneProgramme milestone, plus the features with noneLinks a whole feature to that milestoneLink to milestones
Dependencies— (a form and two lists)Proposes and lists cross-team dependenciesDependencies

The words follow the project's planning words: in the demo project Sprint reads Iterations and Category reads Feature. The PI board has no Delivery block view, because a PI plans its own iterations.


2. Why you would use it​

  • Find the gaps before the review. Not sized, Unassigned and No feature columns put every half-planned story in one place, and the quick filters show only those cards.
  • Balance people, not just iterations. Resource shows each person's load against their own availability, which the iteration totals hide.
  • Tie features to programme events. Milestone shows which of the team's features contribute to the Investor Demo, so the train can see it on the ART Planning Board.
  • Read the plan the way your role needs. A scrum master sizes in Size, a lead assigns in Resource, a product owner checks Feature and Priority — each without disturbing the others, because the view is your own.

3. Where it fits in the event​

The views are there from the moment the team boards open (when the facilitator starts Team breakouts) until the session is closed. Changing a view never changes anyone else's screen: Plan by, Group by and the filters are yours alone. Card fields is also yours, and is remembered for you on this project.

Dropping cards works only while the session is planning or in an adjustment round. During the reviews and after the commit every view is for reading. When the board is read-only, the line above it says why.


4. Step by step: the nine views​

Iterations​

The default view. One column per iteration of the PI with its load, target and capacity, and the Backlog on the left. It is described with its figure in Team boards.

Resource​

Figure 1 — Plan by Resource: one column per person, with what they carry against what they have.

One column per person, plus Unassigned. Drag a card onto a person to assign it. The header shows what the person carries against their availability and a chip such as UNDER 41% or an overload warning. This view counts people's time, so it shows days or hours even in a story-point session.

Size​

Figure 2 — Plan by Size: drop a story on a size to estimate it.

One column per value of the scale, plus Not sized (Drop on a size to estimate). A story-point session shows the point scale; hours, days and value sessions group by ranges. To size a story with the whole team instead of by one drag, use Planning poker.

Feature​

Figure 3 — Plan by Feature: one column per feature.

One column per feature, plus No feature. The view lists the project's features, including ones another team plans or ones outside this PI; the team's own stories sit in its own features' columns. Scroll right to find them.

Type​

Figure 4 — Plan by Type: how much of the plan is each kind of work.
#ElementWhat it does
1Plan by TypeLays the board out by the live task type
2No typeOne column per task type — tasks with none sit in No type
3A type's columnEach column shows how much of the plan is that kind of work: planned effort and the number of tasks

Priority​

Figure 5 — Plan by Priority: one column per priority; here no story has one yet.
#ElementWhat it does
1Plan by PriorityLays the board out by the task's priority
2No priorityOne column per priority — here every story still has none, so there is one column
3CountEach column counts its stories — 1 task, 8 tasks — and their size

Status​

Figure 6 — Plan by Status: the live status of every story.
#ElementWhat it does
1Plan by StatusLays the board out by the task's live status in the project
2Status columnOne column per task status — during PI Planning most stories are still in Backlog
3CountEach column counts its stories and their size, as in Priority

Type, Priority and Status are facts of the live task, not part of the plan, so their columns take no drops. Change a type, priority or status on the task itself (the key on the card opens it).

Milestone​

Figure 7 — Plan by Milestone: features, not stories, are placed on a milestone.

On a PI board this view works on features. The left column holds the team's features with no milestone; each milestone of the programme (defined on the Roadmap) has a column with its date. Drag a feature onto the milestone it contributes to and every story of that feature on this board contributes to it. Drag it back to the left to clear it. A feature whose stories point at different milestones is marked mixed; drop it on one milestone to line them all up.

Dependencies​

Figure 8 — Plan by Dependencies: propose a dependency and see what the team needs and gives.

A PI dependency is always between teams. This view has a quick form — this team's story, another team's story, Needed by, an optional note and Add (push it when ready) — and two lists, [Team] needs and Other teams need from [Team]. The whole workflow, from draft to accepted, is in Team boards.


5. Field and control reference​

Group by​

Figure 9 — Group by: cut every column into lanes.
#ElementWhat it does
1Group bySplits every column into horizontal lanes by a second dimension
2Lane optionsLanes by Resource, Size, Feature, Type, Priority or Status — or None

Plan by Iterations with Group by Resource gives a grid of iteration × person: a quick way to see who is over in which iteration. Moving a card into another lane changes the lane's property as well — for example a drop in another person's lane assigns the story to them. Lanes by type, priority or status take no drops.

Card fields​

Figure 10 — Card fields: up to three extra lines on every card.
#ElementWhat it does
1Card fieldsOpens the list; the number is how many fields are on
2Field listTick up to three fields to show on every card — saved for you on this project

Besides the plain task fields the list offers worked-out lines drawn with a small bar, such as Progress (done of estimate), Spent vs estimate, Subtasks done and Time to due date. The choice follows you to another browser; it does not change anyone else's cards.

Filters, Find a task and one person's cards​

Figure 11 — The filter row, the search box and the person picker.
#ElementWhat it does
1FiltersOpens or closes the filter row
2Feature, status and priorityShow only the cards of one feature, one live status or one priority
3MilestoneShow only the cards that contribute to one milestone
4Quick filtersUnestimated (no size yet), Unassigned (nobody planned on it), Drifted (the live task changed since the board was seeded; the count is in brackets)
5WarningsOnly cards with a warning or a conflict
6Find a task…Find a task by key or title; the × clears it
7Person pickerEveryone, Unassigned, or one person's cards

Clear at the end of the row resets every filter. In Resource, Size, Feature, Type, Priority and Status an extra picker, In …, narrows the board to one iteration: its tasks, and each person's capacity in it.


6. Who may change which view​

The project's Roles & permissions rule book (Project settings → PI Planning) says, for every role, what it may change on its own team's board and on other teams' boards. Each right maps onto one view.

RoleOwn team's board, by defaultOther teams' boards, by default
Release Train EngineerEvery viewEvery view
Product owner, scrum master, team lead, team memberEvery viewDependencies only (and risks in the panel)
Product Manager, System Architect—No view (risks and objectives in the panel)
Business Owner—No view (risks in the panel)
Observer—Nothing

When you hold any right on a board, the line above it reads You can plan on this board. When you pick a view whose right you do not hold, the same line adds Your role cannot change this view — pick another Plan by. and the cards cannot be dragged in that view. This is why, with the default rule book, a member of Atlas looking at Phoenix's board reads You can plan on this board. (their role holds the Dependencies and Raise & ROAM risks rights on other teams' boards) and still sees that message in Iterations. Turn off Opens other teams' boards for a role to keep its people on their own board.


7. Worked example: Tom checks Phoenix's plan view by view​

During Team breakout #1 Tom Becker, Phoenix's scrum master, goes through the board before the draft plan review.

  1. Size. In Size, two stories sit in Not sized. He drags Address autocomplete onto 3 SP; for Cache catalogue for offline browse the team disagrees, so he runs planning poker.
  2. Resource. In Resource, Sync conflict resolution is still in Unassigned. He drags it onto Chen Wei and sees Chen's header move towards his availability.
  3. Group by. Back in Iterations, he sets Group by Resource: Iteration 1 shows Arjun Rao carrying the 8 SP one-tap checkout. The team decides that is fine; the over-capacity is a story-point problem, not a person problem.
  4. Milestone. In Milestone, he drags Mobile Checkout 2.0 onto Investor Demo (10 Nov). Every story of that feature on Phoenix's board now contributes to the demo.
  5. Filters. He opens Filters and switches on Unestimated and Unassigned: the board is empty, so every story is sized and assigned.
  6. Card fields. He ticks Feature so every card names its feature on the big screen.

At the review the board answers the questions management asks, without Tom changing anyone else's view.


8. The admin contract​

Must be in placeWhereWhat happens without it
The rule book's rights per roleProject settings → PI Planning → Roles & permissions (Roles and permissions)The defaults in section 6 apply
Planning wordsProject settings → Planning → Words (Project planning settings)The views read Sprints and Category
Task types and prioritiesThe project's task configurationType and Priority show only No type / No priority
MilestonesThe project's RoadmapPlan by Milestone has only the column of features with no milestone
Features given to the teamFeatures & teams (Features and teams)Feature and Milestone have nothing of the team's to place

9. Downstream effects​

  • Moves made in Iterations, Resource, Size, Feature and Milestone change the team's draft plan exactly like a move in Iterations: they reach the project's tasks only at merge & commit.
  • Sizes set in Size or by poker drive the capacity panel and the draft plan review's load figures.
  • Features linked to a milestone show against that milestone on the ART Planning Board.
  • Plan by, Group by and filters change only your screen; card fields are saved for you alone.

10. Don't confuse this with…​

  • Plan by on the Planning page — the single-planner page has the same row, plus a Delivery block view and a dependency canvas. A PI board hides those; a PI dependency is always between teams.
  • The team panel — risks, objectives and dependency answers are not views; they live in The team panel.
  • Group by vs Plan by — Plan by decides the columns; Group by adds rows inside them.

11. Troubleshooting​

What you seeWhyWhat to do
Your role cannot change this view — pick another Plan by.Your role lacks the right for this view on this boardUse a view you may change, or ask the RTE to adjust the rule book
Cards will not move in Type, Priority or StatusThese views read the live task and take no dropsChange the value on the task itself
Your story is not in FeatureThe view lists every feature of the projectScroll right to the team's own features
Milestone has no milestone columnsThe project has no milestones yetAdd them on the Roadmap
Resource shows days in a story-point sessionResource counts people's timeRead story points in Iterations or Size
Card fields lost after switching projectThe choice is saved per projectPick the fields again for this project
Fewer cards than expectedA filter, a search or a person is setPress Clear, empty Find a task… and set Everyone