The team panel
What this page is — a guide to everything around the stories on a PI team board: the team panel on the right (Adjust, Risks, Objectives, Dependencies and SoS), the Add a dependency drawer, the team's goal per iteration under the board, the banners that say the plan was sent back or must be reworked, and the plan's full screen.
What it is for — keeping a team's risks, promises and answers to other teams next to the plan they belong to, so the team writes its objectives while it can still see what it has planned and answers a dependency while it can still see where the work sits.
The problem it solves — when risks live in one spreadsheet, objectives in a slide and dependencies in a chat, a team commits to Shoppers pay with a saved card in one tap without noticing that the story it needs from Atlas is still unanswered, and the RTE learns about the Apple Pay approval risk only at the final plan review.
Route: Orbit Ops → PI Planning → open a session → Team boards → the panel at the right of the board · Permission to view: Open PI Planning sessions read-only: brief, team boards, program board, risks, discussion, objectives and review. · Permission to change: Take part in a PI session as a team member: move cards on your own team's board, post, raise risks, propose cross-team dependencies, demo and vote., plus the matching right in the project's rule book
1. What the panel holds
The panel starts collapsed as a narrow strip of icons. Press an icon, or the chevron, to open it on that tab; the chevron at its top right collapses it again. Open or closed is remembered in this browser.
| Tab | Holds | Shown |
|---|---|---|
| Adjust | The management adjustments that concern this team: To answer, Your team, The whole train | From the moment management shares its review until the plan is committed |
| Risks | The team's risks, at Team level and at ART level | Always |
| Objectives | Committed and Uncommitted PI objectives, with planned and actual business value | Always |
| Dependencies | This team waits for and Other teams wait for us | Always |
| SoS | The team's answers to the Scrum of Scrums checkpoints | While the teams plan, and through the reviews |
At the foot of each tab a link opens the matching session tab — Open ART Risks, Open the Objectives tab, Open the ART Planning Board, Open Scrum of Scrums — where every team's items are listed together.
2. Why you would use it
- Objectives written next to the plan. The team sees its iterations while it phrases what it promises.
- Risks tied to stories. A risk links to the stories it threatens and is counted on their cards.
- Dependencies answered where the work is. The other team's lead accepts or declines from its own board.
- The RTE hears about trouble at once. An Issue on a Scrum of Scrums checkpoint turns red on the RTE's overview the moment it is set.
3. Where it fits in the event
| Moment | What the panel does |
|---|---|
| Briefing | Objectives can already be drafted; the rest waits for Team breakouts |
| Team breakout #1 (Day 1) | Raise team risks, write objectives, add and push dependencies, answer the SoS checkpoints |
| Draft plan review and management review | Risks, objectives and dependencies stay open; the board itself is read-only |
| Team breakout #2 (Day 2) | Adjust appears once management has shared its review; business owners score PBV; team risks can be placed at ART level |
| Final plan review, confidence vote | The Plan sent back or Plan rework banner tells the team what to change |
| After the commit | Read only; ABV (actual business value) is scored after the PI |
4. Step by step
Adjust: answer management's decisions
When the RTE shares the management review, a banner above the board reads, for example, 4 management adjustments for Phoenix · all answered (or · 1 to answer), with Show them. Show them opens the panel on Adjust. To answer holds the changes the team accepts and applies, or adjusts by hand; Your team the other adjustments that touch it; The whole train the business priorities, actions and risks for everyone. See Planning adjustments.
Once the team has answered, the answer shows as Applied · name or Adjusted by hand · name. While the session is open, the team's people who may answer it — and the RTE — see an Undo icon beside that chip. Undo asks Undo this answer?, puts back what Accept and apply changed on the boards (nothing changes for Adjusted by hand), and returns the decision to To answer. What exactly is put back is described on Management review.
Objectives
| # | Element | What it does |
|---|---|---|
| 1 | Panel tabs | Risks, Objectives, Dependencies and SoS. On Day 2, once management has shared its review, an Adjust tab is added first |
| 2 | Committed | Objectives the team commits to deliver. + adds one: type it in business terms and press Enter. Drag an objective between the sections; click its title to correct it in place |
| 3 | PBV | Planned business value, 1–10 on a ten-stop slider. Set by the business owners (or the RTE) from Team breakout #2 on Day 2; greyed out with a tooltip before that |
| 4 | ABV | Actual business value, scored after the PI. Disabled during planning |
| 5 | Uncommitted | Stretch objectives: planned, not promised |
| 6 | Open the Objectives tab | Goes to the session's Objectives tab, with every team's objectives |
The bin on an objective deletes it after a confirmation (Delete this objective?). Writing objectives needs the PI objectives right. See Objectives.
Risks
Raise a risk opens the risk drawer (title, impact, ROAM state, owner, linked stories). A team risk stays on the team's board and does not appear on the session's Risks tab, which lists only ART-level and programme-level risks. The ↑ button places a team risk at ART level and ↓ brings it back. Team members with the Raise & ROAM risks right can do that from Team breakout #2 on Day 2; the RTE at any time. The pencil edits the risk, its ROAM state and its linked stories; only its author or the RTE can delete it, after the confirmation Delete this risk?. See Risks and ROAM.
Dependencies
This team waits for lists the team's dependencies; drafts are dashed and carry Push, and the pencil edits one. Other teams wait for us lists what other teams pushed to this team, where the lead or scrum master answers with ✓ (your team will deliver it in time) or ✗ (your team cannot commit to it). Only the person who created a dependency, or the RTE, sees the bin that removes it.
Add a dependency from the panel
| # | Element | What it does |
|---|---|---|
| 1 | This team's story (waits) | Your team's story that waits. Already filled in when you start from a card's link icon; fixed once saved |
| 2 | Waits for team | The team it waits for — one button per other team in the session that your role may open |
| 3 | Its | On one of their stories, or a whole feature. Their stories are grouped by the iteration they are planned in; once you pick one the drawer says where it is planned, or Not planned yet |
| 4 | Needed by | When it is needed: an iteration of the PI, or Any time. A red line warns when the other team planned it later |
| 5 | What is needed, and why | Optional, up to 500 characters |
| 6 | Add dependency | Adds it as Draft — not pushed. After Push it shows on both teams' boards until they agree it |
The full workflow, from draft to accepted, is in Team boards.
SoS
For each checkpoint the team picks not started, in progress, done or Issue. An issue asks for a note (What is the issue? (the RTE reads this)) and stays red, Waiting for the Release Train Engineer, until the RTE marks it addressed; then the line reads Addressed by … — mark it Done when it is sorted. Who marked each answer is shown beside it. Only this team and the RTE mark it. See Scrum of Scrums.
The team's goal per iteration
| # | Element | What it does |
|---|---|---|
| 1 | [Team]'s goal per iteration | How many goals are set; click the heading to open or fold the list |
| 2 | A goal | One line per iteration — joined with the other teams' goals into the iteration's goal at the merge |
A goal is saved when you leave the field. It also shows in quotes under the iteration's header on the board. Writing goals needs the Iteration goals right; without it the fields are greyed (No goal yet).
Banners: plan sent back, plan rework
| # | Element | What it does |
|---|---|---|
| 1 | Plan sent back | The Business Owners sent the plan back in the final plan review: who decided, and what to rework |
The banner shows the latest decision on this team's plan from the Final plan review until the plan is committed. When a confidence vote starts a plan rework, the yellow Plan rework banner replaces it, with the reasons and Our plan is reworked — ready for the re-vote (the team's people with the Plan into iterations right, or the RTE). See Plan rework.
Plan full screen
| # | Element | What it does |
|---|---|---|
| 1 | Leave full screen | Leave plan full screen (or press Esc) |
| 2 | The plan | The board fills the screen; the team panel stays open on the right |
The ⤢ button at the right of the line above the board enters full screen. The facilitator keeps the agenda's start or close button in the full-screen header, so the event can move on without leaving the board.
5. Field reference
| Field | Control | Required | Validation | Who may change it |
|---|---|---|---|---|
| Objective title | Text field, Enter to add | Yes | Up to 300 characters | PI objectives right, from briefing to the end of adjustments |
| PBV | 1–10 slider | No | 1–10, or cleared | Business owners and the RTE, from Team breakout #2 |
| ABV | 1–10 picker | No | 1–10 | The RTE or a PI Planning manager, after the commit |
| Risk ↑ / ↓ | Button | — | — | Raise & ROAM risks right from Team breakout #2; the RTE at any time |
| SoS status | Picker | — | Issue asks for a note, up to 500 characters | This team and the RTE |
| Iteration goal | Text field per iteration | No | Saved on leaving the field | Iteration goals right |
| Dependency note | Text area | No | Up to 500 characters | Dependencies right |
| Undo (Adjust tab) | Icon button beside an answer, with a confirmation | — | Not for an answer applied before Undo was available; not once the session is committed or closed | The team's people who may answer the decision, and the RTE |
6. Worked example: Phoenix's panel on Day 2
- Maya shares the management review. Arjun sees 4 management adjustments for Phoenix · 1 to answer, presses Show them and, in Adjust, applies the decision to postpone Offline mode.
- In Objectives, Sofia Alvarez, a business owner, sets PBV 10 on Shoppers pay with a saved card in one tap.
- In Risks, Arjun presses ↑ on Apple Pay merchant approval may take 3 weeks; it now shows on the session's Risks tab, where it is later marked Mitigated.
- At the final plan review Sofia sends the plan back. The board shows Plan sent back by Sofia Alvarez: Move Apple Pay out of Iteration 1 — it is over capacity. The team moves the story and updates the Iteration 1 goal, Saved-card checkout end to end.
- Maya puts the board full screen on the room's display while Phoenix presents its reworked plan.
7. The admin contract
| Must be in place | Where | What happens without it |
|---|---|---|
| Rights per role | Project settings → PI Planning → Roles & permissions (Roles and permissions) | The defaults apply: team roles hold every right on their own board |
| Business Owners named on the session | The session's setup (Create a session) | Only the RTE can score PBV |
| Scrum of Scrums checkpoints | The session's Scrum of Scrums tab | No checkpoints on the list yet. |
| A shared management review | Management review | No Adjust tab |
8. Downstream effects
- ART-level risks appear on the session's Risks tab and in ROAM.
- Objectives with their PBV feed the Objectives tab, the confidence vote and the Post-PI roll-up.
- Accepted dependencies become real task dependencies at the commit; goals become each iteration's goal.
- SoS issues turn red on the RTE's Scrum of Scrums overview.
9. Don't confuse this with…
- The session's Risks and Objectives tabs — every team's items; the panel shows one team's. See Risks and ROAM and Objectives.
- Plan by Dependencies — a board view with a quick form; the panel's tab is the list with the answers. See Team board views.
- Propose a dependency on the ART Planning Board — task to task between features on the programme board. See ART Planning Board.
10. Troubleshooting
| What you see | Why | What to do |
|---|---|---|
| No Adjust tab | Management has not shared its review, or the plan is committed | Wait for the RTE to share it |
| SoS tab missing | It shows only while the teams plan and through the reviews | Use the Scrum of Scrums tab afterwards |
| PBV greyed out | Business value is set by business owners or the RTE, from Team breakout #2 | Agree the value with them on Day 2 |
| ABV greyed out | Actual value is scored after the PI | Score it after the commit |
| ↑ on a risk greyed out | Team risks move to ART level from Team breakout #2 | Ask the RTE, or wait for Day 2 |
| No bin on a dependency | Only its creator or the RTE removes it | Ask them |
| Goal fields greyed | Your role lacks Iteration goals, or the board is read-only | Ask the scrum master or the RTE |
| The panel is closed every time | It is remembered per browser | Open it once in this browser |
| No Undo icon beside an answer in Adjust | You may not answer this decision, or the session is committed or closed, or the answer was applied before Undo was available | Ask the team's lead or the RTE; otherwise change the board by hand |
| This change was applied before it could be undone — change the board by hand. | Nothing was recorded to put back for that answer | Move the stories or the feature back on the board yourself |